Banner

Projects

By applying unique solutions to increase the safety and longevity of our environment.

Chicago polyurethane grouting

The Job

This Chicago polyurethane grouting project is located at BNSF’s Willow Springs Intermodal yard, a critical facility in United States’ freight rail network. The facility is colocated with a large UPS trucking operation. BNSF has very tight time lines for transferring containers from inbound trains to UPS. There are dozens of crossings within the facility, which is primarily concrete pavement.

The Challenge

80 StarTrack modular grade crossing panels across 10 different crossings in the facility experienced settlement. The settlement was affecting the safe operation of yard trucks, causing delays in container transfer times.

Because of the 24/7/365 operation, and very tight performance times, there was no tolerance for downtime.

The Solution

CJGeo proposed grouting the affected panels with CJGrout-48NHL. 48NHL is best for differential settlement correction in high load applications, such as heavy haul rail. It cures within a few minutes, which allows immediate resumption of rail traffic and truck traffic.

CJGeo mobilized a polyurethane grouting crew with extensive modular grade crossing repair experience and grouted the 10 crossings over a period of five days onsite. This Chicago polyurethane grouting project did not affect rail traffic, yard truck operations, or performance metrics.

Speak With An Expert

Facing a similar challenge? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Savannah Tunnel Abandonment

The Job

This Savannah tunnel abandonment job is part of the JW Marriott Plant Riverside conversion. It’s an adaptive reuse hotel project of a decommissioned power plant in Savannah, Georgia. As a thermal generation facility, there are extensive water tunnels below the structure. The cast in place tunnels are part of the piled foundation.

The Challenge

As part of the conversion from thermal power generation to luxury hotel, the tunnels posed a maintenance concern. Due to concerns about inducing settlement with traditional flowable fill, the designer specified EPS Geofoam blocks. These would have effectively eliminated loads, but were deemed impossible to install.

The Solution

Someone onsite had heard of cellular concrete, so reached out to CJGeo. CJGeo evaluated the layout of the tunnels, isolation methods from the river, and designed a mix which would ensure both complete filling of the structures without adding any additional load.

CJGeo placed approximately 930CY of 20lb/cuft CJFill-UL cellular concrete over a period of three days to complete the Savannah tunnel abandonment. Because CJFill-UL is highly mobile, demo debris from the access holes for building bulkheads was left in the tunnels, and encapsulated with the CJFill-UL.

Speak With An Expert

Facing a similar challenge? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Nashville Basement Backfill

The Job

Nashville Yards is a block-wide new build project in downtown Nashville, Tennessee. With multiple underground levels of parking, this Nashville basement backfill excavation is more than 30′ below grade in spots. The excavation walls are a combination of blasted rock and soil nail walls.

The Challenge

The designer wanted to reduce lateral loading on the basement walls as much as possible. Due to the irregular face of the blasted rock & soil nail walls, lightweight aggregate would have been very difficult to install and compact, and would have applied lateral loads for the life of the structure. Flowable fill would have been easy to install, but applied too much lateral loading during installation if done in practical pour volumes.

The structural engineer determined that 25lb/cuft cellular concrete would be the best backfill material. The project volume was approximately 1500CY, and the maximum fill depth was 30′.

The Solution

CJGeo mobilized a mobile batch plant which uses colloidal mixing to the site. Due to the extremely high quality mixing, the crew placed CJFill-Ultra Lightweight up to 10′ deep per pour. This included three pours 10′ deep and 250CY each to complete this Nashville basement backfill project on time.

Speak With An Expert

Facing a similar challenge? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

8′ CMP Joint Grouting

The Job

A spec warehouse was planned for a vacant piece of land which had 1700LF of 8′ CMP running through it. The pipe was 10 years old. Because the site was vacant, there was no maintenance. Nearly every joint showed signs of soil infiltration, and there were massive sinkholes along the entire alignment. Given the depth, size, and short work window, the contractor sought out a CMP joint grouting repair alternative to replacement.

The Challenge

To avoid replacing the entire run of pipe, the joints had to be sealed. There were 80 pipe joints and 12 pipe to structure joints to seal. The pipe crossed under a roadway, and then crossed the site at an angle. The downstream end of the pipe transitioned to new 96″ RCP.

The Solution

In preparation for the repair, CJGeo had to educate the town, contractor, owner & consulting engineers that polyurethane grouting is an effective CMP repair method.

CJGeo mobilized a polyurethane grouting crew to the the site. Over the course of a week onsite, the crew performed all of the CMP joint grouting.

CJGeo used CJGrout 20SDB geotechnical polyurethane. 20SDB is a high mobility geotechnical polyurethane, so seeks out and fills even the smallest of voids outside of pipes. Because it’s highly mobile, it doesn’t deflect or damage the CMP that needs repair.

The manholes also had significant defects. Made of non-parged sewer brick, they leaked extensively. To address the widespread infiltration through the structures, CJGeo sprayed the interior of each structure with CJGrout 60FDC. 60FDC is a hybrid polyurethane/polyurea spray coating. For durability, the 60FDC was coated with polyurea. The 20SDB, 60SDB & polyurea coating were all installed using the same equipment, significantly reducing costs.

Speak With An Expert

Facing a similar challenge? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Veranda St Bridge Infill

The Job

This bridge infill work was part of Maine DOT’s Veranda Street Bridge Replacement Project, in Portland, Maine. Using rapid bridge replacement, the project took a three span bridge and converted it to a single span bridge.

The Challenge

To manage settlement due to up to 80′ of underlying WOH material, lightweight fill was needed to infill two spans, and backfill the new abutments. The absolute lowest unit weight possible requirement led to a hybrid cellular concrete/EPS fill design. The bulk of the infill is EPS blocks. However, due to the irregular surfaces, piers, etc., and the need for a lightweight load distribution slab, cellular concrete was integral to the design.

The Solution

Over two mobilizations for the bridge infill, through snow and freezing temperatures, CJGeo placed 3200CY of 25lb/cuft CJFill-Ultra Lightweight cellular concrete for abutment backfilling and existing pier infills. Then, CJGeo placed 778CY of 30lb/cuft CJFill-Ultra Lighweight as a topping slab over the EPS fill masses.

To ensure high quality material and minimize weather-related risks, CJGeo used onsite batching to generate the material. A mobile batch plant custom built for generating cellular concrete mixes water and dry bulk cement onsite. The cement paste and foam blend continuously to generate a completely homogenous material. With a slump of around 11.5 inches, both densities of CJFill-Ultra Lightweight cellular concrete were able to flow around all of the existing structures and provide a void-free fill.

Speak With An Expert

Facing a similar challenge? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Atlanta cellular concrete

The Job

This Atlanta cellular concrete installation is part of Atlanta Watershed Management’s Niles Avenue Sewer Improvements project. The project took approximately 2500LF of microtunneling to install a new 18″ sewer main.

The Challenge

A 72″ microtunnel was chosen, which required approximately 1200CY of annular space grouting. Operations were challenged by the pandemic hitting in the middle of the project.

The Solution

CJGeo proposed 30lb/cuft CJFill-UL cellular grout for the annular space grout. This allowed the contractor to avoid mechanical buoyancy control during grouting operations during single lift grouting. Buoyancy control of the carrier was one of the driving factors for using CJFill-Ultra Lightweight for this Atlanta cellular concrete project. Because the tunnels had a good amount of slope on them, grouting in multiple stages would have been impractical. Flowable fill would have floated the carrier pipe, even if it was full of water.

Over two mobilizations, CJGeo generated the cellular grout onsite and placed it via shafts which were up to 40 feet deep. CJGeo chose wet batch generation due to the project volumes.

Speak With An Expert

Facing a similar challenge? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Norfolk polyurethane grouting

The Job

This Norfolk polyurethane grouting project is located on a military base. The medical clinic on a military base was being renovated. As part of the renovation, the 650sqft elevated slab front porch needed to be replaced. The slab “sounded hollow,” and the presumption was that there were nominal voids below the slab.

The Challenge

At the start of demolition, the demolition contractor determined that the voids below the slab were closer to 3′ deep. This presented a safety problem for the demolition. The concern was that the slab would fail catastrophically during demolition. The general contractor reached out to CJGeo about ways to reduce the void depth.

The Solution

CJGeo proposed void filling below the slab using CJGrout 20SDB. CJGrout 20SDB is a low exotherm bulk void filling geotechnical polyurethane specifically formulated for deep fill placements without scorching or charring.

CJGrout 20SDB cures to 95% of final strength within a few minutes. Because of this, by the time the crew is packed up to leave the site, the material is effectively completely cured. This is significantly faster than cementitious grouts like flowable fill, and facilitates fast return to service. Because 20SDB is very light, it also reduces the likelihood of inducing settlement compared to traditional flowable fill.

A two person polyurethane grouting crew mobilized to the site and placed approximately 2,900lbs of CJGrout 20SDB in a few hours onsite, allowing the demolition contractor to safely resume work.

Speak With An Expert

Facing a similar challenge to this Norfolk polyurethane grouting project? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Industrial Basement Abandonment

The Job

This industrial basement abandonment project is located in Southside, Virginia. As part of an adaptive reuse project of an abandoned industrial site, the former onsite power plant’s stacks were being rehabilitated. Multiple tunnels and basement rooms had to be completely filled.

The Challenge

Due to safety concerns, nobody could enter the basement. No as-builts were available. Camera inspection through holes cored in the ceiling showed significant numbers of passageways and obstructions. The fill material had to be:

  • exceptionally mobile,
  • placed in deep lifts,
  • and as light as possible.

Fill density was a concern because the basement was up to 15′ deep. 150lb/cuft traditional flowable fill would have caused too much anticipated settlement. Settlement of the basement structure could potentially cause settlement or movement of the adjacent smoke stacks.

The Solution

CJGeo proposed 25lb/cuft cellular concrete for the lightweight fill material. Using onsite colloidal batching, CJGeo can place material up to 20′ deep in a single lift, without consolidation. Because CJFill-Ultra Lightweight is so lightweight, the entire 15′ deep basement fill dead load was the same as from just 2′ of traditional flowable fill. For this application, Aerlite-iX was the most appropriate cellular concrete foaming agent.

CJGeo mobilized a 150CY/hour dry batch plant to the site after staging 300 tons of cement onsite using our in-house cement pig & trucking operation. Over four days onsite, CJGeo place 2700CY of CJFill-Ultra Lightweight material to complete the industrial basement abandonment.

Speak With An Expert

Facing a similar challenge? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

New Jersey Grade Crossing Stabilization

The Job

This grade crossing stabilization project is located in Edison, New Jersey. A precast modular grade crossing (Oldcastle StarTrack) crossing developed significant pavement deterioration. NJDOT directed the railroad to stabilize and lift the panels and then patch the adjacent asphalt.

The Challenge

The grade crossing sees up to 8 trains per day (heavy industrial service), and crosses a four lane arterial highway. So, there wasn’t any allowable downtime. Because of this, traditional cementitious grout was not a viable option. Cementitious grouts generally need hours to reach strength, so can significantly disrupt train schedules, and require long lane closures for vehicles.

The Solution

CJGeo proposed grouting the panels using CJGrout 60NHL. 60NHL is a geotechnical polyurethane grout specifically formulated for heavy applications such as rail and aircraft loads. A CJGeo polyurethane grouting crew mobilized to the site and in fewer than 2 hours onsite restored the affected panels. Another name for this process is concrete raising.

This grade crossing stabilization project did not require ground improvement grouting. The cause of the settlement was the bedding fines washing out, so only shallow grouting was necessary.

Speak With An Expert

Facing a similar challenge to this grade crossing stabilization project? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Warehouse Floor Joint Stabilization

The Job

This floor joint stabilization project is located in Ashland, Virginia. About two months after occupying a new warehouse, the tenant identified two joints where the floor “popped” at a joint when a forklift drove over them. After consulting the plans, the owner determined that the joint wasn’t doweled, and needed warehouse floor joint stabilization.

The Challenge

Both affected joints were on main, high frequency travel pathways within the warehouse. So, any repairs had to be done quickly, and with zero impact to operations.

The Solution

CJGeo proposed undersealing the two joints, which had experienced slab curl, with high density geotechnical polyurethane grout. In fewer than three hours onsite, CJGeo undersealed the joints with CJGrout 20SDB, load tested them, and demobilized. There were no impacts to operations of the facility during this warehouse floor joint stabilization repair.

Undersealing is the best method for addressing slab curl joint popping. Grinding or polishing, an alternative method does not stop the movement. Filling joints with rigid joint filler can temporarily stop movement, but typically results in fatigue and cracking. Undersealing for slab foundation repair completely fills the voids below the floor so that the floor can’t move. If the curl is significant enough that it affects ride, polishing can be done afterwards to address ridges.

Speak With An Expert

Facing a similar challenge to this warehouse floor joint stabilization project by CJGeo? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Top