Banner

Projects

By applying unique solutions to increase the safety and longevity of our environment.

Ohio Annular Space Grouting

The Job

This Ohio annular space grouting project is located in Akron. It is part of the Northside Interceptor, being constructed by Granite Construction. The total project budget is about $215 million, to construct 6,660 linear feet of 16.5′ diameter segmental liner tunnel.

While the main tunnel is single pass, there are multiple tie-ins to the structure, some of which are open cut, and another which is a microtunnel. The microtunnel is 530 linear feet of 48″ pipe.

The Challenge

Plans call to grout the annulus between the carrier pipe and microtunnel casing with 600psi at 28 day material. A lean concrete mix to achieve this compressive strength would be significantly heavier than water. This can cause significant headaches managing carrier pipe buoyancy, as the heavier the grout, the greater the uplift during grouting.

The Solution

CJGeo grouting the micro tunnel annular space.

CJGeo proposed a 55lb/cuft CJFill-Standard mix to meet the compressive strength requirement, while minimizing carrier pipe buoyancy. Because the proposed material is less dense than water, filling the carrier pipe with water during the grouting process keeps the carrier pipe in place.

A CJGeo dry batch cellular grout crew placed 119 cubic yards of 55lb/cuft CJFill-Standard over two hours to fill the annular space in a single lift. Cellular concrete is also referred to as foamed concrete fill.

Speak With An Expert

Facing a similar challenge to this Ohio annular space grouting project? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Indiana Pipe Abandonment

The Job

This Indiana pipe abandonment project is located in Anderson. Anderson is in central Indiana, near Indianapolis. The project is a water main relocation out of a park.

The Challenge

Plans call for safe loading the pipe being replaced. It’s important to fill abandoned utilities to prevent them from being groundwater conduits, or eventually failing completely. This can cause significant amounts of settlement, and transport soils long distances, neither of which is desirable.

The Solution

Generating 200CY/hour of CJFill-Ultra Lightweight cellular grout onsite.

Using traditional flowable fill would have required close to 10 access points to place material into the pipe. This would have torn up a bunch of the park that the pipe ran though, and taken quite a bit of time.

CJGeo proposed filling the pipe from a single access point near the middle, using CJFill-Ultra Lightweight cellular grout. The beauty of cellular grout for abandonment is that it’s pumpable thousands of feet. In this case, the first run was 770 linear feet. The second run was 488 linear feet.

It would be possible to grout the entire run in a single stretch, however there was already an excavation at this point to blind a connecting pipe, and there was a nearby fire hydrant.

CJGeo sent a dry batch plant to the site, and the grouting work took less than an hour of pumping to completely fill the pipe.

Speak With An Expert

Facing a similar challenge to this Indiana pipe abandonment project? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

New York Pipe Abandonment

The Job

This New York pipe abandonment project is located in Newburgh, New York. Newburgh is on the Hudson River, about an hour upstream of New York City.

The Challenge

As part of a sanitary sewer upgrade project, 5,399 linear feet of gravity sewer ranging from 6″ to 24″ was specified for grout filling. The highest volume run was a 1,022 linear feet continuous run of 24″ pipe. The longest run was 1,469 linear feet of 18 inch” pipe. Each run did have intermediate manholes, but most manholes were a few hundred feet apart.

The Solution

Pumping cellular grout through a placement pipe.

Traditionally, the customer would have dumped flowable fill in the manholes in an attempt to completely fill the lines by gravity. However, many of the manholes were off road, and some of them were hundreds of feet apart. This makes gravity discharge of flowable fill into manholes unreliable for ensuring complete fill.

CJGeo proposed performing the abandonment grouting using 30lb/cuft CJFill-Ultra Lightweight cellular grout. Since cellular grout will flow much further at nominal pressures, CJGeo was able to place through multiple manholes at once, which significantly reduced access requirements.

Due to the relatively low volume on this project, continuous wet batch was the best method for generating the cellular grout for this project. Wet batch uses slurry delivered by ready mix truck, with Aerlite-iX added downstream of CJGeo’s slurry pump.

Speak With An Expert

Facing a similar challenge to this New York pipe abandonment project? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Indoor Pool Abandonment

The Job

This indoor pool abandonment project is located in West Virginia, at Concord University. A swimming pool built in the 1970’s was no longer in use, and had sat empty for years. As part of a renovation, the pool had to be filled in order to pour a slab and prepare the room for other uses.

The Challenge

Like many buildings in the mountains, the original site sloped. A retaining/basement wall passes through the building close to the deep end of the pool, whose sloped floor roughly follows the original grade of the site. The structural engineer had to concerns about backfilling the pool:

  • increasing lateral loads on the adjacent basement wall if a heavy, granular material was used for the fill material
  • causing settlement by filling the pool with material heavier than the water it was designed to hold, and which the underlying soils had seen for years

The original bid had two options: filling the pool entirely with 57 stone, or filling it entirely with 2lb/cuft EPS blocks.

The Solution

Geofoam blocks would have addressed both the axial and lateral load challenges. However, EPS would take a few weeks to import, cut, and place. 57 stone would have been least expensive, but increased lateral and axial loads beyond those of water.

CJGeo proposed a value engineered alternative to fill the bottom 70% of the pool with 25lb/cuft CJFill-Ultra Lightweight low density cellular fill (LDCF), topped with 57 stone, and then a new floor slab. The structural engineer, architect and owner all accepted the proposed change. The general contractor was excited to save weeks out of their schedule.

A single CJGeo dry batch cellular concrete crew performed the work over two days. The first lift, of 400 cubic yards took about two hours to place, and was roughly 6 feet deep. The second lift, around 350 cubic yards, also took about two hours to place. The day after CJGeo wrapped up, the general contractor was able to start placing the 57 stone on top of the CJFill-Ultra Lightweight fill.

Speak With An Expert

Facing a similar challenge to this indoor pool abandonment project? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

WWTP Tunnel Curtain Grouting

The Job

This WWTP tunnel curtain grouting project is located in Syracuse, New York. It is located immediately adjacent to the southern shore of Onandaga Lake in an area that is historical infill.

The Challenge

CJGeo performing curtain grouting.

A 700 foot long, 17 feet deep utility tunnel runs through the treatment plant site. Inside are numerous site utilities, including large diameter waste lines, along with many smaller diameter chemical and treatment lines.

Over time, the tunnel walls have developed leaks, accentuated by the highly variable fill material outside of the structure. When it rains, water enters the tunnel, which has roughly three feet of cover.

The Solution

As part of a large project at the plant, plans call for curtain grouting the length of the tunnel with polyurethane grout. Curtain grouting can be done two ways:

  • through the structure walls, using holes drilled through the structure, or
  • from the surface, using tubing inserted down along the exterior face of the wall

In this case, the interior walls of the tunnel were not uniformly accessible due to the number of utilities mounted on the wall. CJGeo designed a grouting program using the sacrificial tubes from the surface method. The advantage of this method in this case was that the density of utilities on the inside face of the structure didn’t affect the ability to uniformly introduce grout along the outside surface of the structure.

A CJGeo chemical grouting crew placed nearly 1300 gallons of single component polyurethane resin on this WWTP curtain grouting project. The work took about three weeks start to finish. The general contractor had removed the backfill and installed a new waterproofing membrane over the tunnel lid and extending down the walls about one foot on each side.

Speak With An Expert

Facing a similar challenge to this WWTP tunnel curtain grouting project? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Penstock Void Grouting

The Job

This penstock void grouting project is located near Hopkinton, New Hampshire. It is located at a small hydroelectric power plant that has been in service for more than 40 years.

The Challenge

CJGeo worker drilling holes through a metal pipe as part of a penstock void filling project.

This hydro-electric plant’s two original parallel penstocks are wooden. Sometime after original construction, 6.5′ ID steel liners were installed inside the original wooden penstocks.

Typically, when pipes are slip lined, the annular space between the ID of the original pipe and OD of the liner is grouted. However, in this case, the annulus was left open.

The steel pipes are nearing the end of their service life, and require rehabilitation. Plans called for installing a shotcrete liner. Specs called for a cementitious grout with 30 minute working time placement behind the steel pipes prior to spraying shotcrete.

The Solution

The marine contractor performing the shotcrete lining reached out to CJGeo about performing the annular space grouting with cementitious grout. CJGeo’s engineering & operations teams evaluated the project documents and site conditions and determined that there was a very high risk of grout escaping the annulus and making it to the adjacent waterway. This was due to the unknown condition of the original wood penstock, minimal cover over the pipes, and unknown, but potentially open graded backfill material.

CJGeo proposed an alternative, using CJGrout 22SHV geotechnical polyurethane grout to perform the penstock void grouting. CJGeo’s alternative material proposal was accompanied by load calculations from our geotechnical professional engineer confirming that despite strength significantly less than the specification requirement, that CJGrout 22SHV provided multiple factors of safety beyond the actual loads the annulus would see.

Upon approval by the owner’s consulting engineering team, CJGeo mobilized a confined space polyurethane grouting crew to the site. Over two days, the crew successfully grouted the annular space between the steel and wood penstocks. The following day, the contractor began installing reinforcement and prepping the steel pipe surface for shotcrete application.

Speak With An Expert

Facing a similar challenge to this penstock void grouting project? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Ohio Polyurethane Grouting

The Job

This Ohio polyurethane grouting project by CJGeo was for a short line railroad near Scio, Ohio. The railroad received numerous complaints from motorists about a settled grade crossing. The settlement of the precast grade crossing was great enough to also require a speed restriction for rail traffic.

The Challenge

CJGeo polyurethane grouting crew members using a pneumatic drill

When this precast grade crossing settled, the clips holding the rail to the crossing panels broke. This allowed significant differential settlement between the various panels. The differential settlement was up to two inches.

In order to install new clips, the panels generally have to be within 3/8-inches of the adjacent panels’ elevation. If any debris has accumulated between the rail foot and bearing surface of the precast panels, which in this case were Oldcastle’s StarTrack.

The Solution

Having repaired multiple precast crossings for this short line, they reached out to CJGeo about performing this Ohio polyurethane grouting project. CJGeo proposed CJGrout 40NHL geotechnical polyurethane grout to the railroad. CJGrout 40NHL is formulated for high dynamic loading environments, and is excellent for different settlement correction of thick pavements.

CJGeo mobilized a polyurethane grouting crew to the site. Due to relatively low traffic on the line, the customer was able to provide an eight hour window for the repair, and the DOT allowed a complete road closure, as the settlement affected both lanes, with the centerline being the worst spot on the crossing.

CJGeo crews used mechanical assistance to address some of the worst differential settlement. Cleaning the accumulated debris between the rail foot and panels was key to facilitating complete correction of the differential settlement. After CJGeo wrapped up the polyurethane grouting, the railroad’s maintenance-of-way crew installed new clips, replaced the boots, and patch the adjacent asphalt.

Speak With An Expert

Facing a similar challenge to this Ohio polyurethane grouting project? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Flooded Shaft Grouting

The Job

This flooded shaft grouting project by CJGeo is located outside of Washington, DC at a data center site. As the 60″ microtunneling machine was entering the retrieval shaft, a piece broke off of the secant pile wall, and tore the seal. This resulted in water infiltration of around 600 gallons per minute into the shaft. The machine was recovered, but the shaft filled with nearly 15 feet of water in a matter of hours.

The casing crown has roughly 20 feet of cover, and is about 15 feet below the ground water level. The ground in the area is a mix of clays and sands. The tunnel is primarily in the underlying fractured rock. For the last 30 feet of tunnel before the secant pile receiving shaft, the tunnel is in a mix of weathered rock and sandy clay.

The Challenge

Having used CJGeo in the past to address high volume leaks into shafts, the tunneling contractor reached out to CJGeo for this flood shaft grouting problem. The primary constraints were:

  • time – the project was already behind schedule
  • water management – any groundwater was considered contaminated

Typically, grouting a leak such as this would be as simple as throwing bigger pumps into the shaft, dewatering it, then grouting the leak from inside the shaft. However, because of the costs associated with treating potentially very high volumes of water at this site, this wasn’t an option.

The Solution

CJGeo proposed, and then successfully performed, a two stage grouting program. Primary grouting was done using CJGrout 35NHV61 geotechnical polyurethane on a Saturday. The CJGrout 35NHV61 was installed immediately behind the secant pile wall through three holes drilled from the surface to intercept the over cut. Grout injection through these holes resulted in grout return to the retrieval shaft. Off gassing also showed up at the launch shaft. This indicates that the rapid inflow of water during the flooding event had washed out some of the mud in the over cut.

After completion of the plural component primary seal injection, CJGeo dye tested the primary grouting program. This was done through Tube-A-Manchette grout pipes installed along the tunnel alignment, further out from the shaft. No dyed water returned to either shaft.

The following day (Sunday), CJGeo performed permeation grouting using colloidal silica through the TAM grouting tubes. This secondary grouting program served two purposes:

  • seal any rock fractures that weren’t penetrable by the higher viscosity plural component polyurethane grout
  • replace any overcut mud washed out during the initial flooding event

Speak With An Expert

Facing a similar challenge to this flooded shaft grouting project? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Underground Storage Tank Fill

The Job

This underground storage tank fill project by CJGeo is located at a food manufacturing facility near Harrisonburg, Virginia. The tank is 30 thousand gallons, and designed to store diesel to feed backup power generation for the facility. As part of an equipment upgrade, the tank is no longer in use, and had to be filled.

The Challenge

The best way to address unused underground storage tanks that aren’t removable is to fill them. If left empty and out of mind, abandoned empty tanks can cause serious problems, such as sudden collapse, which can significantly affect operations. Unfilled, out of use tanks can also accumulate groundwater, leading to potential environmental liabilities.

The Solution

CJGeo proposed 30lb/cuft CJFill-Ultra Lightweight (CJFill-UL) to fill the tank. CJFill-Ultra Lightweight is easily hand and machine excavatable to ensure that when the tank is removed in a few years that it’s not difficult.

While easily hand excavatable, CJFill-Ultra Lightweight still provides more than adequate compressive strength. In this case, total loads were just a few hundred pounds per square foot, whereas the CJFill material provides more than 17ksf of unconfined compressive strength. The American Concrete Institute publishes a removability modulus calculation which helps to quantify the ease of removal of controlled low strength materials, read more about it and how it relates to cellular concrete here.

It took CJGeo less than an hour to completely fill this tank. Confirmation of complete fill was uniform material venting from the tank vent ports.

Speak With An Expert

Facing a similar challenge to this underground storage tank fill project? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

RCP Joint Sealing

The Job

This RCP joint sealing project is located near Charlottesville, Virginia. The polyurethane grouting work was subcontracted to CJGeo as part of an on call contract for stormwater structure and dam maintenance with a municipality.

The Challenge

Pavement distress of an asphalt roadway over a small dam prompted an inspection of the triple barrel 48 inch RCP structure passing through the dam. Upon inspection, significantly less water was flowing through the pipes than was flowing through the downstream spillway.

On each of the three pipes, water was flowing out of the endwall around the RCP inverts. There was relatively little cover on the pipes. This would make open cut replacement relatively simple. However, the roadway is the primary access to a neighborhood. Thus, a trenchless grouting repair to address the joint failures and piping was optimal.

RCP Joint Sealing Featured
Typical RCP repair work using geotechnical polyurethane.

The Solution

CJGeo worked with the on-call contractor, and owner’s dam engineering consultant to design a grouting program that not only addressed the piping and joint leaks, but also the voids in the fill material between the pipes and roadway.

Over the course of two days onsite, a CJGeo polyurethane grouting crew grouted each of the three pipes using CJGrout 35NHV61 geotechnical polyurethane. 35NHV61 is provides adequate bearing capacity for typical roadway loading, performs identically in flowing water and dry environments, and is certified for potable water contact.

Speak With An Expert

Facing a similar challenge to this RCP joint sealing project? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Top