Banner

Projects

By applying unique solutions to increase the safety and longevity of our environment.

Valve Vault Infiltration Grouting

The Job

As part of the Purple Line project in Maryland, a large diameter water line was relocated. The tie-in was done inside a 10′ diameter vault that was about 20′ deep, and done in a liner plate shaft. The vault structure was precast.

The Challenge

The vault structure wasn’t concentric in the shaft. This left little room to pour the closure around the pipe penetrations. One of the penetrations leaked, causing the structure to completely fill with water. Per specifications, it needed to be dry.

The Solution

CJGeo proposed grouting the infiltration points with CJGrout-35NHV61. 35NHV61 is a hydroinsensitive, plural component geotechnical polyurethane, certified for potable water contact.

CJGeo mobilized a three person crew to the site, and was able to stop the various leaks in the structure in a few hours.

Steam Tunnel Lightweight Backfill

The Job

As part of the expansion and renovation of the steam plant at Western Carolina University, a section of existing steam tunnel needed to be uncovered to install a new wall. The wall needed to be backfilled, and due to the condition of the tunnel, the lighter the backfill the better.

The Challenge

The site was exceptionally tight, and the location was more than 30 minutes from the closest ready mix plant. The backfill depth was nearly 15 feet, but the project was only about 1200CY, so doing 2′ lifts would have been slow and expensive.

The Solution

CJGeo proposed a CJFill-UL as a value improvement over the organic foaming agent cellular concrete that was specified. The architect and structural engineer approved the proposed change.

CJGeo mobilized a four person crew and a 200CY/hour mobile batch plant, and completed the work in three pours over two days. The CJFill-UL was generated using a synthetic foaming agent that can be placed up to 20 thick at a time, and is generated onsite directly from bulk cement, so isn’t dependent on ready mix plant locations.

Illinois Spillway Grouting

The Job

A spillway serving as a dam for a lake owned & maintained by a property owner association outside of Carbondale, Illinois stopped having water flowing over the spillway. The property owners determined that the lake was draining through voids under the spillway slab. This made them concerned about destabilization of the spillway, which was the sole access for six homes.

The Challenge

The flow velocity was rather high, and immediately on the other side of the spillway was a 30′ cliff, that the water was designed to spill over as a waterfall. Given the extraordinary difficulty of retrieving any material washed over the waterfall, the grout had to have an exceptionally fast set. It also needed to provide adequate bearing capacity for the roadway slabs.

The Solution

CJGeo proposed grouting below the spillway with CJGrout 40NHL, which is usually used for differential settlement correction. CJGrout 40NHL performs well for differential settlement correction because it reacts very quickly, and is used for medium duty lifting, such as highway pavement, so it would provide more than enough bearing capacity.

The owners were very excited that it would be significantly less expensive to grout the existing spillway than to have someone local install a portadam and replace the entire structure. CJGeo mobilized a single polyurethane grouting crew to the site, and they stopped the leaks and kicked all the water flow over the spillway in a single day.

I-64 Soundwall Backfill

The Job

VDOT’s I-64 widening project is a multi-phase widening of Interstate 64 between Richmond & Newport News. This work occurred as part of Segment 2.

The Challenge

Approximately 150LF of a combination sound & retaining wall needed to retain more than 10′ of backfill. In order to keep the drilled foundation size consistent along the alignment, the backfill material needed to be significantly lighter than the soil backfill used in other segments, where there was minimal retained depth.

The material needed to be freely-draining and less than 40lb/cuft.

The Solution

CJGeo proposed backfilling the affected wall segments with 30lb/cuft CJFill-UL. Used extensively by VDOT for backfilling the retained zones of MSE walls, CJFill-UL provides significantly better bearing capacity than soils or aggregates, and once cured does not apply lateral loads to the structures it is placed against.

CJGeo placed approximately 200CY of CJFill-UL to backfill the wall in two pours, each approximately 5′ thick. The contractor was able to place the pavement subbase on top of the material the following day.

Willow Springs Crossings

The Job

BNSF’s Willow Springs Intermodal yard is a critical facility in United States’ freight rail network. The facility is colocated with a large UPS trucking operation, and BNSF has very tight time lines for transferring containers from inbound trains to UPS.

The Challenge

80 StarTrack modular grade crossing panels across 10 different crossings in the facility experienced settlement. The settlement was affecting the safe operation of yard trucks, causing delays in container transfer times.

Because of the 24/7/365 operation, and very tight performance times, there was no tolerance for downtime.

The Solution

CJGeo proposed grouting the affected panels with CJGrout-48NHL. 48NHL is specially formulated for differential settlement correction in high load applications, such as heavy haul rail.

CJGeo mobilized a polyurethane grouting crew with extensive modular grade crossing repair experience and grouted the 10 crossings over a period of five days onsite. The grouting was done without affecting rail traffic, yard truck operations, or performance metrics.

Savannah Tunnel Abandonment

The Job

The JW Marriott Plant Riverside is an adaptive reuse hotel project of a decommissioned power plant in Savannah, Georgia. As a thermal generation facility, there are extensive water tunnels below the structure. The tunnels were cast in place during original construction, and integrated into the pile supported foundation.

The Challenge

As part of the conversion from thermal power generation to luxury hotel, the tunnels needed to be filled. Due to concerns about inducing settlement with traditional flowable fill, the designer specified EPS Geofoam blocks. These would have effectively eliminated loads, but were deemed impossible to install.

The Solution

Someone onsite had heard of cellular concrete, so reached out to CJGeo. CJGeo evaluated the layout of the tunnels, isolation methods from the river, and designed a mix which would ensure both complete filling of the structures without adding any additional load.

CJGeo placed approximately 930CY of 20lb/cuft CJFill-UL cellular concrete over a period of three days. Because CJFill-UL is highly mobile, demo debris from the access holes for building bulkheads was left in the tunnels and encapsulated with the CJFill-UL.

Nashville Basement Backfill

The Job

Nashville Yards is a block-wide new build project in downtown Nashville, Tennessee. With multiple underground levels of parking, the basement excavation is more than 30′ below grade in spots. The excavation walls are a combination of blasted rock and soil nail walls.

The Challenge

The designer wanted to reduce lateral loading on the basement walls as much as possible. Due to the irregular face of the blasted rock & soil nail walls, lightweight aggregate would have been very difficult to install and compact, and would have applied lateral loads for the life of the structure. Flowable fill would have been easy to install, but applied too much lateral loading during installation if done in practical pour volumes.

The structural engineer determined that 25lb/cuft cellular concrete would be the best backfill material. The project volume was approximately 1500CY, and the maximum fill depth was 30′.

The Solution

CJGeo mobilized a mobile batch plant which uses colloidal mixing to the site. Due to the extremely high quality mixing, the crew placed CJFill-Ultra Lightweight up to 10′ deep per pour. This included three pours 10′ deep and 250CY each.

8′ CMP Joint Grouting

The Job

A spec warehouse was planned for a vacant piece of land which had 1700LF of 8′ CMP running through it. The pipe was installed when the site was first prepped, approximately 10 years prior to construction. Because the site was vacant, there was no maintenance. Nearly every joint showed signs of soil infiltration, and there were massive sinkholes along the entire alignment.

The Challenge

To avoid having the replace the entire run of pipe, the joints needed to be sealed. There were 80 pipe joints and 12 pipe to structure joints that were affected.

The Solution

CJGeo mobilized a polyurethane grouting crew to the the site. Over the course of a week onsite, the crew sealed all of the joints. As part of the joint sealing, the voids around the pipe were filled with CJGrout 20SDB geotechnical polyurethane. After the grouting work was done, the site contractor backfilled the sinkholes and washouts with soil.

Veranda St Bridge Infill

The Job

Maine DOT’s Veranda Street Bridge Replacement Project, in Portland, Maine. Using rapid bridge replacement, the project took a three span bridge and converted it to a single span bridge.

The Challenge

To manage settlement due to up to 80′ of underlying WOH material, lightweight fill had to be used to infill two spans, and backfill the new abutments. The absolute lowest unit weight possible requirement led to a hybrid cellular concrete/EPS fill design. The bulk of the infill was performed using EPS blocks. However, due to the irregular surfaces, piers, etc., and the need for a lightweight load distribution slab, cellular concrete was integral to the design.

The Solution

Over two mobilizations, through snow and freezing temperatures, CJGeo placed 3200CY of 25lb/cuft CJFill cellular concrete for abutment backfilling and existing pier infills. A 778CY 30lb/cuft topping slab was then poured over the EPS fill masses.

Niles Avenue Annular Space Grouting

The Job

Atlanta Watershed Management’s Niles Avenue Sewer Improvements project involved approximately 2500LF of microtunneling to install a new 18″ sewer main.

The Challenge

A 72″ microtunnel was chosen, which required approximately 1200CY of annular space grouting. Operations were challenged by the pandemic hitting in the middle of the project.

The Solution

CJGeo proposed 30lb/cuft CJFill-UL cellular grout for the annular space grout. This allowed the contractor to avoid mechanical buoyancy control during grouting operations during single lift grouting.

Over two mobilizations, CJGeo generated the cellular grout onsite and placed it via shafts which were up to 40 feet deep.

Top