Banner

Acrylic Grouting

By applying unique solutions to increase the safety and longevity of our environment.

SOE Closure Manchette Grouting

The Job

This SOE closure Manchette grouting project is located in Alexandria, Virginia. It is part of the RiverRenew project, a large CSO project.

The Challenge

As part of this project, a diversion structure and drop shaft were being installed to pull flow off of an existing sewer tunnel. The box tunnel is around 8′ wide. The SOE will facilitate installation of the diversion chamber. Excavation within the SOE called for closing the gap between slurry wall panels. This is to be done under the existing structure with steel lagging.

However, the closure is below ground water table. The “marsh” deposits soils require stabilization prior to excavation. The conceptual design from the owner called for permeation grouting tied into an underlying clay layer. The clay layer is approximately 50′ below existing grade.

The Solution

CJGeo proposed performing the permeation grouting to cut off ground water flow and stabilize the soils for excavation using an acrylic grout. Due to the relatively deep required depth, traditional percussion driven installation tubing wasn’t possible.

To ensure accurate placement at depth, CJGeo used the TAM grouting method. TAM grouting, or Tube-a-Manchette, uses special grout casing installed by drilling to grout through.

CJGeo performed this SOE closure Manchette grouting work over a period of two weeks.

Speak With An Expert

Facing a similar challenge to this SOE closure Manchette grouting project? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Pregrouting for Hand Mining

The Job

This large CSO project in Alexandria, Virginia required pregrouting for hand mining. The hand mining was to install a new pipe below an existing influent tunnel, which is on piles. The hand mined tunnel was to connect two a secant pile shaft to a slurry wall pit, which are roughly 25′ apart.

The Challenge

The challenges on this project included:

  • no drilling allowed without pre-probing
  • 3′ thick secant pile walls
  • unknown exact pile support layout of influent tunnel
  • fully saturated soils
  • potential debris in backfill under existing influent tunnel

The Solution

CJGeo proposed performing the permeation grouting using acrylate. Acrylate is exceptionally low viscosity, so well suited to the organic, fine-grained soils. Previous permeation grouting on the project was done with acrylamide. However, acrylamide is neurotoxic and carcinogenic, so the owner was happy to learn about acrylate, which has very similar properties, but is not neurotoxic or carcinogenic.

To avoid drilling, CJGeo developed a pushed/driven probe grouting installation. This approach uses 1/2″ diameter steel tubing driven to depth, and then grouted through during extraction.

The 3′ thick secant pile walls didn’t pose too much of an issue, clearance holes were drilled with hand-held percussion drills.

Drilling wasn’t allowed. The owner and design team were concerned about potentially hitting and damaging the pile foundation. Because there was the potential for debris, there would be no way to distinguish debris from a pile until it was potentially too late. By using groutable probe rods, CJGeo avoided all of this risk.

The fully saturated soils had relatively low permeability, and the site was constrained on two sides by the existing SOE structures. Performing permeation grouting when below the water table you’re limits the placement rate by the ability to displace the existing groundwater. Because of the water-tight walls on two sides of this pregrouting for hand mining application, take was slower than originally anticipated.

Speak With An Expert

Facing a similar challenge to this project? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Launch Shaft Permeation Grouting

The Job

This launch shaft permeation grouting project is located in Fort Myers, Florida. As part of a utility installation project, a 60″ MTBM was being launched from a shaft sunk in the middle of a nest of buried utilities, adjacent to an arterial roadway. Utilities included water, sewer, ITS, traffic signals, and others. The MTBM launch elevation was approximately 18′ below ground water.

The Challenge

The shaft installation contractor and adjacent open cut utility installations had experienced flowing sands, which had proven problematic. The tunneling contractor knew that without increasing the stability of the soils adjacent to 60″ hole they needed to cut in the sheet pile shaft walls, there would likely be significant loss of ground into the shaft, potentially damaging the adjacent utilities and roadway.

Soils excavated from the shaft were primarily fine sands, silty sands, and silt. Previous attempts at grouting the same soils with a prepolymer chemical grout had proven unsuccessful.

The Solution

CJGeo determined that acrylic grout would be the most appropriate. Acrylate can bind the soils together very well. This makes flowing silty sands stand vertically during cutting of the launch hold in the sheet pile wall.

Because acrylic grouts have single digit viscosities, they are able to permeate very find grained soils with ease, ensuring uniform stabilization.

CJGeo performed the launch shaft permeation grouting via holes cut in the sheet piling, and treated an approximately 8CY mass of soil. In addition to grouting the soils immediately adjacent to the launch hole, CJGeo performed leak stop grouting on numerous nuisance leaks throughout the joints of the sheet pile shaft.

Speak With An Expert

Facing a similar challenge to this project? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

MTBM Recovery Grouting

The Job

This MTBM recovery grouting project is located in Florida. When a 42″ MTBM stopped advancing under the shoulder of I-75 in Miami, Florida, the tunneling contractor had to sink a shaft adjacent to the roadway, and then hand mine in to recover the machine.

The Challenge

The MTBM was stalled approximately four feet from where the recover shaft was sunk. The face of the machine was under the shoulder. The tail of the machine was under the outside lane of the interstate. The machine was approximately 15′ below ground water level. There was also extensive ground water infiltration into the sheet pile rescue shaft. Further complicating things, an intelligent transportation system duct bank runs right over where the machine came to a halt.

In order to ensure that the ground would be stable to facilitate hand mining in from the shaft while avoiding settlement of the interstate, the tunneling contractor reached out to CJGeo about increasing the stability of the soils.

The desire was to increase the stability of the soils. However, the treated soils had to be hand excavatable by divers working in a casing slightly larger than the MTBM. Soils in the desired treatment zone included lime rock, course sands and silty sands.

The Solution

CJGeo determined that acrylic grout would be the most appropriate to bind the soils together. This method would also significantly reduce their permeability, but still facilitate hand excavation in an underwater confined space.

The failure mechanism of the MTBM was unknown. So, CJGeo grouted the zone between the MTBM face and the rescue shaft. We then grouted a collar around the entire MTBM machine in case the machine needed to be completely uncovered.

CJGeo successfully performed the permeation grouting, then divers excavated back to the machine, freeing it. The grouted face held once the receiving ring was installed and the sheet pile wall cut. The treatment zone soil was easily excavatable for the divers.

In addition to grouting the soils, CJGeo’s crew also performed grouting of numerous nuisance ground water leaks through various joints in the sheet pile shaft.

Speak With An Expert

Facing a similar challenge to this MTBM recovery grouting project? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Top