Banner

Projects

By applying unique solutions to increase the safety and longevity of our environment.

Garden State Parkway grouting

The Job

This Garden State Parkway grouting project is located near Middletown, New Jersey. As part of ongoing large diameter culvert rehabilitations and replacements, four new bored stormwater crossings and the original culvert they replaced needed to be grouted. The tunnels ranged from 120″ down to 74″, for a total of 312CY, and the abandonment required 405CY.

The Challenge

Grout needed to meet the minimum strength requirements of the owner, and ideally needed to be light enough to facilitate single lift annular space grouting.

The Solution

CJGeo’s preconstruction team worked with the general contractor to design a grouting program which facilitated single lift abandonment of the original culvert, and single lift grouting of the four various annular space runs. CJGeo utilized onsite dry batching to generate 30lb/cuft CJFill Ultra Lightweight cellular concrete.

CJFill is a type of Low Density Controlled Low Strength Material, or LD-CLSM. The “low density” comes from using preformed foam, in this case Aerlite-iX, as a substitute for aggregate. This significantly reduces the unit weight, which exponentially increases pumpability. In this case, all 405 cubic yards of abandonment grout were placeable at once.

Because CJFill LD-CLSM is significantly lighter than water, each annular space grouting run was doable in a single lift. Filling each carrier pipe partially with water was all it took to facilitate this.

Speak With An Expert

Facing a similar challenge to this Garden State Parkway grouting project? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Lightweight Plaza Fill

The Job

Lightweight plaza fill for a private age restricted high rise new build in Tysons Corner, Virginia. Tysons Corner was historically an office heavy area of Fairfax County, but this project, along with many others, is increasing the amount of residential real estate in the area.

The Challenge

To manage dead loads over the four story parking deck, while achieving a landscape design requiring up to five feet of fill, the designer specified 20lb/cuft CJFill-High Permeability cellular concrete for the plaza fill material. The material had to be permeable, and placed up to 600′ from the closest access point for a plant. The deck elevation is about 30′ above the laydown area.

The total square footage of placement needed to be around 17,000 square feet. EPS foam blocks were an alternative fill material. However, EPS would have been exceptionally time consuming and expensive to install.

The Solution

CJGeo mobilized a 200CY/hour dry batch plant and crew, who generated up to 500CY/day for placement via hoses and a boom pump to successfully fill the plaza areas. Total project volume for this lightweight plaza fill was approximately 2200CY.

All material is onsite from dry bulk cement, with zero exposure to the hit or miss ready mix concrete market. An onsite cement storage pig allows overnight raw material delivery and staging, to eliminate traffic disruption.

The 20lb/cuft CJFill-High Permeability Low Density Controlled Low Strength Material placement was formed by the site concrete contractor. After the CJFill-HP had set, the site concrete contractor poured exposed aggregate sidewalks directly on top of the CJFill-HP. Other areas of the deck were backfilled with engineered lightweight soil, and then planted with extensive landscaping.

Speak With An Expert

Facing a similar challenge? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

CBBT Sheet Pile Pregrouting

The Job

This sheet pile pregrouting project is located in the Chesapeake Bay. The Chesapeake Bay Bridge Tunnel’s Parallel Thimble Shoal Tunnel Project is constructing a second tunnel parallel to the original to reduce traffic congestion. All launch & receiving work is on man-made islands in the Chesapeake Bay. The islands are dense with utilities, equipment and operations facilities associated with the existing tunnel, which is in continuous use.

The Challenge

During previous phases, installation of sheet piling for tunneling activities and other driven elements induced consolidation of the loose sandy fill on the islands. This was causing settlement of duct banks, pavements and other structures, which were remedied by CJGeo using polyurethane compaction grouting.

In this case, sheet piles had to be driven immediately adjacent to the roadway. This is in order to excavate the receiving pit for the tunnel boring machine. The construction team was concerned about inducing settlement of the adjacent roadway. They reached out to CJGeo about performing compaction grouting under the footing for the original tunnel’s portal wall. This was after the wall had been demolished down to grade.

The Solution

CJGeo performed compaction grouting utilizing an NSF-certified potable water contact plural component CJGrout 35NHV polyurethane grout. Cutoff criteria was 0.10 inches of movement of the foundation or adjacent roadway. Upon completion of the compaction grouting by CJGeo, sheet piling installation started. There was only nominal movement of the foundation and roadway.

Speak With An Expert

Facing a similar challenge to this sheet pile pregrouting work by CJGeo? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Hollow Abutment Filling

The Job

This hollow abutment filling project is located in Buckland, Massachusetts. Buckland is a small town on the east end of the Berkshires. The bridge conveys a rural highway over a drinking water impoundment. As part of a bridge rehabilitation for MassDOT, two hollow abutments were specified for filling. This would turn the structural approach/departure slabs into slab on grade. The alternative would have been to completely replace the structures. Filling them with traditional weight backfill would have caused significant settlement.

The Challenge

It was up to 30′ from the bottom of slab to the underlying soil which had originally been installed to backfill the abutments. The lightest possible material capable of providing sufficient support to the pavement was required. This would reduce the loads applied to the bridge from the backfill. Due to the very constrained access (a few cored holes through the deck, and a few square foot port cut into each abutment face), the lightweight material had to be self-consolidating (placed as a fluid).

Due to integrated beams for the structural slabs, there were 12 different individual pockets which were up to 2′ tall. Each had to be vent independently during the final lift. Four of were under live traffic because the road had to have one lane open at all times.

The Solution

CJGeo worked with the general contractor to formulate a plan to vent the individual pockets from outside of the open lanes. This helps to ensure a complete fill without requiring a complete road closure. Over the course of two mobilizations, CJGeo placed 2,840CY of 25lb/cuft CJFill-Ultra Lightweight to fill the abutments.

Speak With An Expert

Facing a similar challenge to this hollow abutment filling project? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

8″ Pipe Abandonment

The Job

This 8″ pipe abandonment project is located outside of Washington, DC. As part of continuing waterline replacements, a utility contractor in Fort Washington, Maryland, needed to abandon 10,600LF of 8″ water main. The utility and DOT both require grouting of all utilities 6″ and larger taken out of service.

The Challenge

In order to minimize the number of placement points, the grout needed to be exceptionally mobile.

The Solution

CJGeo proposed a 30lb/cuft CJFill-Ultra Lightweight (CJFill-UL) cellular grout, and worked with the client to design a grouting plan that would allow grouting all 10,600LF of pipe from just three access points. CJGeo performed the grouting over a period of two days, with no additional excavation required from the customer other than their original tie ins/disconnects.

By cutting the pipe at three locations, it was split into roughly equal segments. Each of around two thousand six hundred feet. 30lb/cuft CJFill-Ultra Lightweight is easily pumpable this distance without yield loss.

To do this same work with flowable fill would have required approximately thirty five access points. This would be to split the pipe into roughly thirty six segments around three hundred feet, each. Even then, pumping flowable fill three hundred feet through eight inch pipe is very difficult. By using CJFill-Ultra Lightweight for this pipe abandonment project, the general contractor saved about two weeks off of their schedule, and tens of thousands of dollars.

Speak With An Expert

Facing a similar challenge to this 8″ pipe abandonment project that CJGeo performed using cellular grout? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Union County Annular Space Grouting

The Job

This Union County annular space grouting project is located in North Carolina, near Charlotte. Due to a rapidly increasing population, Union County, North Carolina installed a new raw water intake. It required a nearly 11 mile long raw water line to supply a water treatment plant.

The Challenge

There are dozens of road crossings along the alignment. 17 crossings are jack & bore, and require annular space grouting per NCDOT requirements. Given the length of the project, there weren’t any ready mix providers who could cover this entire annular space grouting in North Carolina project.

The Solution

CJGeo has multiple NCDOT approved mix designs, for CJFill-UL. CJGeo sourced material from two different ready mix providers. Each annular space on all crossings was grouted per NCDOT requirements. CJGeo has approved mix designs with the North Carolina Department of Transportation that cover the entire state. From the Outer Banks to Asheville, Raleigh/Durham, Wilmington & Charlotte, CJGeo has you covered.

The density for this work was 30lb/cuft CJFill-Ultra Lightweight. 30lb/cuft CJFill-Ultra Lightweight breaks above NCDOT’s minimum 125psi at 28 day unconfined compressive strength requirement for annular space grout. Because the project volume on this job is relatively low per crossing, CJGeo used ready mix for the raw slurry. Ready mix typically isn’t best for large placements. But for small, spread out placements like this project, is a great fit.

Speak With An Expert

Facing a similar challenge to this Union County annular space grouting project by CJGeo? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

North Carolina Tub Crossing Repairs

The Job

This tub crossing repairs project is located in Charlotte, North Carolina. Fifty two OldCastle StarTrack panels at four different grade crossings settled to the point of requiring slow orders at the crossings. In order to restore the track to normal speeds, the settlement had to be corrected.

The Challenge

Due to scheduling constraints with rail traffic, with very short windows on weekend nights, the owner elected to have the repairs completed during a single weekend shutdown period. While this allowed for longer work periods, it also meant that four crossings needed to be repaired in fewer than 24 hours.

The Solution

CJGeo mobilized two polyurethane grouting crews to the system, and grouted two crossings each during two shifts. All 52 of the panels were stabilized and lifted back to grade using CJGrout 48NHL, which allows for immediate resumption of rail traffic, from light rail to heavy haul.

Polyurethane grouting is also sometimes called structural polymer grouting. Regardless of name, the process works very well where fast return to service is important. In the case of tub crossing repairs, grout must set very quickly in order for rail traffic to resume. CJGrout 48NHL achieves 95% of its ultimate strength in fewer than 15 minutes.

Speak With An Expert

Facing a similar challenge to this tub crossing repairs project by CJGeo? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Spillway Bridge Grouting

The Job

This spillway bridge grouting project is located in Toano, Virginia. Toano is between Williamsburg and Richmond. Two DOT-maintained bridges crossing two privately owned dam spillways had to be closed because of extensive undermining of the spillways.

The undermining was allowing nearly all of the flow to happen below the spillway slabs. This caused large sinkholes to form adjacent to and under the roadway pavement. It also led to some settlement of the spillway slabs.

The Challenge

There was very little room to work–just under 4′ of clearance below the bridge beams. Also, the velocity of the water through the voids below the structure was quite high.

The Solution

CJGeo proposed a combination of plural component polyurethane grouting to address the water flows and voids, and hydrophobic chemical grout placed directly into cracks. A single CJGeo grouting crew was able to complete the repairs in a day (roughly 2500sqft of work, and approximately 4500lbs of CJGrout 35NHV61 polyurethane, plus 30 gallons of hydrophobic chemical grout). Dye testing during and after the grouting work confirmed that no more leaks were present under or around the spillway structures.

Speak With An Expert

Facing a similar challenge to this spillway bridge grouting project by CJGeo? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

24″ Water Main Abandonment

The Job

This 24″ water main abandonment project is located in Fairfax, Virginia. Fairfax County is part of the rapidly expanding Northern Virginia region. As part of a large transportation project, 2000 linear feet of 24″ water main were being relocated out of a highway right-of-way.

The Challenge

Due to phasing, the old water main was located under the existing roadway and could not be accessed, except for at one point near the center of the run. So, the abandonment grout had to meet VDOT’s minimum strength requirements for flowable fill, and be pumpable up to 1100LF at low pressure. VDOT’s minimum 28 day unconfined compressive strength requirement is 30psi.

The Solution

CJGeo grouted each run of pipe using 30lb/cuft CJFill-Ultra Lightweight low density controlled low strength material. Each CJFill-UL placement took fewer than two hours, and required no additional traffic control, disruptions to other construction activities, or help from the utility contractor after they installed the bulkheads.

The 28 day compressive strength of 30lb/cuft CJFill-Ultra Lightweight cellular grout is 150psi. This significantly exceeds VDOT’s minimum compressive strength for controlled low strength material (flowable fill).

Speak With An Expert

Facing a similar challenge to this 24″ water main abandonment project that CJGeo completed using CJFill-Ultra Lightweight cellular concrete? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Grain Silo Tunnel Backfilling

The Job

This grain silo tunnel backfilling project is located in Tampa, Florida. As part of a redevelopment project in downtown Tampa, Florida, a large grain milling facility was moving operations from the downtown port to a new facility further down Tampa Bay.

The Challenge

The facility is immediately adjacent to Tampa Bay. To minimize flood risks, the the entire structure is above grade. This includes the 8′ tall unloading conveyor tunnels. The structure was bears on a mat slab cast over thousands of auger cast piles. The unloading tunnels were only about 10% of each silos footprint. So, the areas long side of the tunnels needed to be filled.

Due to the slipform construction, there was very limited access. So the backfill material around the tunnels needed to be pumpable. Flowable fill was an option, but is very heavy. The design build contractor identified cellular concrete as a potential backfill material. This could save nearly 1ksf of dead load off of the mat foundation.

The Solution

CJGeo worked with the design builder to create a mix design that would minimize the amount of dead load on the foundation, while providing adequate support for the bin floor when fully loaded with grain. Over the course of a few weeks, CJGeo crews placed nearly 7200CY of 25lb/cuft CJFill-Ultra Lightweight cellular concrete. Rodbusters were able to start setting steel the day after completion of the final lift in each of the silos.

Speak With An Expert

Facing a similar challenge to this grain silo tunnel backfilling load reducing fill project by CJGeo? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Top