The Job
Lightweight plaza fill for a private age restricted high rise new build in Tysons Corner, Virginia.
The Challenge
To manage dead loads over the four story parking deck, while achieving a landscape design requiring up to five feet of fill, the designer specified 20lb/cuft cellular concrete for the plaza fill material. The material had to be permeable, and placed up to 600′ from the closest access point for a plant.
The Solution
CJGeo mobilized a 200CY/hour dry batch plant and crew, who generated up to 500CY/day for placement via hoses and a boom pump to successfully fill the plaza areas. Total project volume was approximately 2200CY.