Banner

Polyurethane Grouting Projects

By applying unique solutions to increase the safety and longevity of our environment.

SOE Leak Grouting

The Job

This SOE leak grouting project is located in Alexandria, Virginia. It is part of the RiverRenew project, which is a large CSO tunnel and drop shaft project. This location is immediately adjacent to the Woodrow Wilson Bridge, and the Potomac River.

The Challenge

At a drop shaft location, the contract installed two parallel slurry walls between an existing combined sewer box culvert and a drop shaft to the new tunnel. During excavation of the pit, two high volume leaks, each around 125GPM opened up below the existing conduit.

The customer installed road plates to stabilize the area, and pumped flowable fill behind the road plates. This provided short term stability to the area, but did not address the high velocity flow of water through an unanticipated open graded sand seam that was causing the leaks.

The Solution

CJGeo mobilized a grouting crew capable of performing both high volume geotechnical polyurethane grouting and acrylic permeation grouting at the same time for this SOE leak grouting work. The first step was to install CJGrout 35NHV61 to fill voids which had washed out immediately behind the road plates.

After grouting the bulk voids and slowing the velocity of the leaks, CJGeo installed acrylic grout up to 20 feet behind the slurry wall face. The only way to reliably stop water flow through sands is to bind them together with a very low viscosity grout. The acrylic grout installed on this project has a viscosity less than 10 centipoise. This allows it to uniformly permeate the sands, react into a cooked egg white consistency, and make the treated sands impermeable.

Speak With An Expert

Facing a similar challenge to this SOE leak grouting project? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Apartment Floor Lifting

The Job

This apartment floor lifting project is on a military facility in Washington, DC. During turnover of a unit, the property management company discovered signs of significant settlement affecting the interior floor. There was a significant crack showing through vinyl flooring, and up to 1.5 inch gaps below the baseboard in a carpeted room.

The Challenge

The primary challenge for the general contractor on this project was repairing the floor as quickly as possible. The unit was only going to be unoccupied for about two weeks between tenants. The contractor not only had to repaint, install all new floors, but also had to address this settlement.

The Solution

The general contractor reached out to CJGeo to assess the feasibility of raising the floor using polyurethane grouting. Having worked together in the past, the general contractor knew that CJGeo’s polyurethane grouting process is significantly faster than traditional mud jacking or concrete replacement.

A single CJGeo polyurethane grouting crew took less than a day to complete this apartment floor lifting repair. The total area grouted was around 750 square feet. Using CJGrout 28FDL, the grouting process corrected all of the settlement. Because polyurethane grouts are about 95% lighter than traditional grout and backfill materials, the likelihood of the grout material inducing future settlement is virtually eliminated.

Speak With An Expert

Facing a similar challenge to this apartment floor lifting project? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

48 Inch RCP Joint Repair

The Job

This 48 inch RCP joint repair project is located in Raleigh, North Carolina. The pipe is located at a commercial facility. The slope covering the pipe experienced a slope failure. Upon inspection, six joints were showing signs of soil infiltration and water exfiltration.

The Challenge

The primary challenge for the general contractor on this project was minimizing cost and time. It would have been expensive and disruptive to excavate the pipe. Cover depths were up to 15 feet, and there was a road that would be impacted by excavation, as well.

The exfiltration from the leaking joints was washing away bedding material and adjacent backfill. This caused significant amounts of erosion, and destabilized the slope soils by completely saturating them.

Piping outside of reinforced concrete pipe is an ideal candidate for polyurethane grouting.

The Solution

CJGeo worked with the general contractor and owner’s civil engineering to design a grouting program to repair the pipe. The general concept for this 48 inch RCP joint repair project was to backgrout the pipe with rigid geotechnical polyurethane grout. CJGrout 35NHV61 was the grout of choice; it can be injected directly into flowing water, provides nearly 10ksf in compressive strength, and migrates into both large and small voids with ease.

A CJGeo polyurethane grouting crew took a single day to perform the repair. The average circumferential void around the pipe was nearly nine inches. Cutoff criteria were:

  • grout hole to joint communication
  • cross hole communication

Speak With An Expert

Facing a similar challenge to this 48 inch RCP joint repair project? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Maryland Concrete Lifting

The Job

This Maryland concrete lifting project is located in Frederick, Maryland. The project is for the MARC system, on tracks also used by CSX.

The Challenge

MARC’s Brunswick Line includes a spur to Frederick, which utilizes a freight track that also serves multiple industrial sites, including quarries and concrete plants. As it winds through an industrial area towards the Frederick station, the line crosses multiple arterial roadways. As Frederick grows, traffic is increasing significantly with both cars and industrial truck traffic.

At two crossings, bellies have developed in the precast modular grade crossings. Water collects at the low spots, which then reduces bearing capacity of the base, causing deterioration of the adjacent asphalt pavement. This deterioration causes spalling of the panels, and ride quality problems for motorists.

The Solution

CJGeo’s rail grouting experience includes dozens of precast modular grade crossing stabilization projects. Working with the rail system’s on-call MOW contractor, a CJGeo polyurethane grouting crew grouted each of the two crossings in a day, each.

CJGeo uses CJGrout 48NHL, which is specifically formulated for high dynamic load applications. 48NHL provides multiple factors of safety from a compressive strength perspective, but is slightly elastomeric, which makes it much more durable than mudjacking or traditional cementitious pressure grouting grouts sometimes used to stabilize modular grade crossings on a temporary basis.

Speak With An Expert

Facing a similar challenge to this Maryland concrete lifting project? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Box Culvert Void Filling

The Job

This box culvert void filling project is located near Fredericksburg, Virginia. The Virginia Department of Transportation owns and maintains the structure, which conveys a stream under a rural divided highway. As part of a rehabilitation project, extensive cracking in the structure (a double barrel six foot by six foot box), was being patched with repair mortar, and some cracks epoxied.

The Challenge

At the start of project, the general contractor discovered extensive voids outside of the structure. These voids were allowing significant amounts of the stream flow outside of the box culvert (piping). This was cause for concert regarding the specified repair mortar application and epoxy injection.

The general contractor reached out to CJGeo about filling the voids with grout prior to the patching and repair operation.

The Solution

CJGeo proposed grouting all the voids outside of the box culvert with CJGrout 35NHV61. 35NHV61 is a hydro-insensitive, structural polyurethane grout. Its NSF61 potable water certification makes it excellent for work on drainage structures.

The owner, Virginia’s Department of Transportation, required water testing before, during and after grouting. This water testing specifically looks for MDI. All of the water testing, which was performed by a third party environmental laboratory, found zero MDI in any of the water samples.

It took three days onsite to complete the grouting. Some hairline cracks that were still damp after the bulk box culvert void filling work. CJGeo grouted these cracks with a hydrophilic chemical grout to make them completely dry.

Speak With An Expert

Facing a similar challenge to this box culvert void filling project? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Stormwater Sinkhole Repair

The Job

This stormwater sinkhole repair project is located at a data center near Dulles, Virginia. Within a few months of construction, a depression started over a utility intersection within a street intersection inside the fence. Time showed that asphalt patching wasn’t going to solve the problem, so a geotechnical engineering firm was brought into investigate the sinkhole.

The Challenge

The first step taken was video inspection of all the gravity utilities in the area. None of them were showing any signs of leaks of water or soil. Utilities within the zone of influence of the sinkhole include:

  • stormwater (deepest & largest)
  • fire protection
  • two fiber duct banks
  • three electrical duct banks

Given the shear number and crossing alignments of utilities, and lack of leaks, the presumption was that backfill consolidation over the underlying stormwater structure was the most likely cause of the settlement.

The Solution

Due to the presumed cause of inadequate compaction, the geotechnical engineer recommended polyurethane compaction grouting to the owner. Compaction grouting with polyurethane grout is significantly faster, less disruptive, and less likely to displace adjacent structures than cementitious compaction grouting.

CJGeo proposed using CJGrout 20SDB for this stormwater sinkhole repair project. 20SDB is well suited for filling bulk voids, and has very little expansive pressure, so minimizes the chances of fouling or damaging the adjacent critical utilities.

A CJGeo polyurethane grouting crew was able to complete the repairs over two days onsite.

Speak With An Expert

Facing a similar challenge to this stormwater sinkhole repair project? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Maryland compaction grouting

The Job

This Maryland compaction grouting project is located on East West Highway, in Chevy Chase. A few years after finishing construction of a new mixed use building with underground parking, the public sidewalks began to settle.

The Challenge

A local consulting geotechnical engineer was the first call by the building owner. After reviewing the construction drawings, and visiting the site, the geotech recommended performing a few hand augers. The hand augers were to:

  • confirm the sidewalk construction matched the plans
  • check for bulk voids below the sidewalk
  • confirm the backfill material
  • see just how loose the backfill material was.

The hand augers confirmed that the sidewalk was indeed pavers over asphalt, over a thin concrete mud slab. There were sporadic voids below the mud slab, up to six inches deep. The backfill material was poorly controlled soil, and was relatively loose.

The Solution

Due to the backfill material being relatively loose, and the building being new enough that the soils hadn’t consolidated on their own, the geotechnical engineer recommended polyurethane compaction grouting to the owner. Compaction grouting with polyurethane grout is significantly faster, less disruptive, and less likely to displace adjacent structures than cementitious compaction grouting.

CJGeo proposed using CJGrout 20SDB for this Maryland compaction grouting project. 20SDB is well suited for filling bulk voids, and has very little expansive pressure, so minimizes the chances of fouling or damaging drainage board.

A CJGeo polyurethane grouting crew was able to complete the repairs over two days onsite.

Speak With An Expert

Facing a similar challenge to this Maryland compaction grouting project? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Massachusetts Lightweight Fill

The Job

This Massachusetts lightweight fill project is located at Boston’s Logan International Airport. It is part of Logan Forward continuing improvements to the airport.

The Challenge

As part of this project, the general contractor installed two cast-in-place barrier walls. The space between the barrier walls is between four and nine feet. The walls are curving, have non-vertical faces, and bear on a curving, non-horizontal existing podium slab. The gap between the walls needed to be filled in order to pour a housekeeping slab spanning between the walls.

This work is all on an existing podium structure. So, the fill density between the two walls had to be as low as possible.

The Solution

CJGeo proposed filling between the two walls with CJGrout 20SDB. 20SDB has a similar density and compressive strength to typical expanded polystyrene (EPS, or Geofoam) blocks. However, unlike geofoam blocks, 20SDB:

  • is pumped, so doesn’t require trimming, and fits to any shape
  • expanded onsite, so logistics are significantly simpler
  • cures within a few minutes, so is still quick
  • not affected by petroleum products

A CJGeo polyurethane grouting crew took a single shift onsite to install the 64 cubic yards of CJGrout 20SDB. The general contractor began installing the topping slab the next day.

Speak With An Expert

Facing a similar challenge to this Massachusetts lightweight fill project? Give us a call or send us an email by clicking on the state marker to locate the Preconstruction Manager that services your area.

New Jersey polyurethane grouting

The Job

This New Jersey polyurethane grouting project is located in Creskill, New Jersey. As part of a full gut renovation of the library, the architect specified lifting settled areas of the floor. The floor settlement was affecting approximately 3200 square feet, with settlement up to two inches.

The Challenge

The library building is a slab on grade, with relatively light design loads. The floor is approximately four inches thick, and reinforced with welded wire mesh. The original design to correct settlement was to use mud jacking. Mud jacking works well, but is rather slow, and tends to be very messy. Mud jacking uses cement-based grout pumped under high pressure below concrete to fill voids and push the concrete back up. A downside is that the grout is quite heavy, and the additional weight it adds to already compromised soils can cause additional future settlement.

The Solution

CJGeo proposed using CJGrout 28FDL geotechnical polyurethane grout as an alternative to the specified mud jacking process. CJGeo’s value engineer proposal was based on the following benefits of polyurethane grouting over traditional cementitious grouting:

  • speed – polyurethane grouting tends to be significantly faster than cementitious grouting
  • cleanliness – polyurethane grouting is a very clean process, including dustless drilling, mechanical connections to the slab, and material that scrapes off with a putty knife if it leaks from below a slab
  • density – traditional mud jacking grout is approximately 50 times heavier than in place CJGrout 28FDL. This reduces the likelihood of future resettlement by minimizing the additional load that grout places on the underlying soils.

The architect and structural engineer accepted CJGeo’s value engineering proposal for this New Jersey polyurethane grouting repair. A crew of three CJGeo polyurethane grouting experts completed the repair in less than a day. Because polyurethane cures within a few minutes, the general contractor was able to move on to the next steps in the project very quickly.

Speak With An Expert

Facing a similar challenge? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

North Carolina Compaction Grouting

The Job

This North Carolina compaction grouting project is located at a military facility in eastern North Carolina. To facilitate the renovation of an adjacent office building, the owner installed eight mobile office buildings. Before the mobile offices were put into use, they settled up to three inches. As a result, the owner had to stabilize the structures before moving any equipment and people into the structure.

The Challenge

The site comprises of sand backfill over native loose sands. The eight mobile buildings bear on masonry piers resting on plastic load distribution pads. The piers and pads are on approximately 6′ centers, spread uniformly throughout the structure. The crawlspace is too shallow to safely enter.

The Solution

CJGeo proposed using CJGrout 35NHV to perform compaction grouting below the piers to stabilize the loose soils. 35NHV is a 3.5lb/cuft rigid polyurethane foam. It performs well for void filling and compaction grouting in wet environments.

Special polyurethane grouting rigs generate CJGrout 35NHV onsite. The rigs have hoses up to 400 feet long, which convey the material from the grouting rigs to the placement area. For this project the 35NHV was injected using sacrificial tubing. The tubing passes through holes in the floor through the crawlspace, to roughly 3′ below the pads.

One of CJGeo’s polyurethane grouting crews was onsite for three days to complete this North Carolina compaction grouting project. CJGeo used rotary lasers to monitor the floor elevation over each pier during grouting. The cutoff criteria was movement of approximately 0.25 inches. Then, a carpentry crew jacked and shimmed the beams after the grouting. Finally, a flooring crew restored the flooring afterwards.

Speak With An Expert

Facing a similar challenge? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Top