Banner

Commercial & Industrial

By applying unique solutions to increase the safety and longevity of our environment.

Utility Tunnel Abandonment

The Job

This utility tunnel abandonment project is located in Wilmington, Delaware. Approximately 750CY of subbasement and utility tunnel had to be filled as part of a commercial building adaptive reuse project.

The Challenge

The structural engineer had two concerns:

  • the slab over the basements were to be replaced,
  • tunnel walls required bracing to demo the roof slab
  • the density of the fill needed to be as low as possible to reduce the chances of inducing settlement.

The Solution

CJGeo proposed 25lb/cuft CJFill-Ultra Lightweight low density controlled low strength material. Low density controlled low strength material is a fancy name for cellular concrete. 25lb/cuft CJFill-UL has an average of 80psi compressive strength. Because CJFill-UL cellular concrete is very mobile, there were no issues with filling the tunnel from just a few access points.

With an average cured unit weight of 21lb/cuft, the using load reducing fill material saved approximately 1ksf in dead load relative to conventional fill materials. CJFill-Ultra Lightweight also provides sufficient strength to brace the walls to facilitate floor removal, and also provide adequate bearing capacity for the new floor.

It took a CJGeo cellular concrete crew two days onsite to fill the tunnel and subbasement. Onsite dry batching made up to 100 cubic yards per hour of the 25lb/cuft CJFill-Ultra Lightweight. Material placement was through 4″ cores and an exterior access areaway.

Other types of lightweight fill would have been much harder to install. Foamed glass aggregate or expanded shale aggregate would be practically impossible to compact given the low headroom. The density of expanded shale aggregate is also relatively high, so would not have offered the load savings that 25lb/cuft CJFill-Ultra Lightweight foamed concrete does. EPS is very lightweight, but is very labor intensive in this type of application.

Speak With An Expert

Facing a similar challenge to this utility tunnel abandonment by CJGeo? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Power Station Pipe Abandonment

The Job

This power station pipe abandonment project is between Richmond & Lynchburg, Virginia, along the James River. Dominion’s Bremo Bluff Power Station was taken off line in 2019. As part of complete decommissioning, demolition and site restoration took place in 2022.

The Challenge

Power stations typically have extensive pipes for cooling water circulation. At Bremo Bluff, the buried cooling pipe network consists for four, four foot diameter pipes, connecting to a junction box. Total linear footage of the forty-eight inch pipes is about six hundred linear feet.

Due to the remote location, the demolition contractor knew that it would be difficult to get timely deliveries of the nearly 40 loads of flowable fill needed to fill the pipes.

The Solution

The demolition contractor reached out to CJGeo for consultation on the best type of flowable fill for the pipe abandonment work. CJGeo recommended 25lb/cuft CJFill-Ultra Lightweight. 25lb/cuft CJFill-Ultra Lightweight has a 28 day compressive strength (ASTM C495) greater than 50 psi. This met the owner’s requirements.

25lb/cuft CJFill-Ultra Lightweight is nearly 80% air content. Therefore, each twenty-five ton load of cement delivered to the site turns into nearly 150 cubic yards of finished product. Due to this on-site expansion, instead of needing nearly 40 loads of ready mix flowable fill, the work only needed two loads of cement.

CJGeo generated and placed approximately 300CY of CJFill-Ultra Lightweight cellular concrete to fill the junction box and pipes. CJGeo made all of the material over a few hours onsite, using dry batch generation.

Speak With An Expert

Facing a similar challenge to this power station pipe abandonment project? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Lightweight Tank Foundation

The Job

This lightweight tank foundation installation project is located in Baltimore, Maryland. During an industrial facility expansion, a new blending tank was being installed at the top of a retaining wall. In addition concerns about lateral loading on the wall, the area is generally known to be built with uncontrolled fill over compressible soils, so settlement is a concern.

The Challenge

Due to the presence of industrial waste and debris in the area, light duty deep foundations such as helical piles are generally difficult to install. To avoid inducing settlement, the geotechnical EOR reached out to CJGeo for lightweight fill options to net out the increased weight of the mat foundation and blending tank.

Based on loads, CJGeo suggested a 25lb/cuft cellular grout with a compressive strength of at least 50psi. At this density, the engineer was able to balance all loads with a 4′ deep undercut. The undercut extended a few feet out around the perimeter of the tank foundation.

The Solution

First, the concrete foundation contractor excavated the pit. Then, CJGeo mobilized to the site and placed 110CY of 25lb/cuft CJFill-Ultra Lightweight cellular concrete into the pit. The lightweight tank foundation placement took less than an hour. The foundation contractor was able to start setting steel and forms the following morning.

Speak With An Expert

Facing a similar challenge to the one we solved with this lightweight tank foundation? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Hotel Basement Water Intrusion Grouting

The Job

This basement water intrusion grouting project was at a hotel in Baltimore, Maryland. It had a continuously wet floor in the basement utility room. Water was oozing out from under the power feed bank housekeeping slab. The housekeeping slab sits directly on top of the floor slab. There were two presumed point sources:

  • the unsealed joint between the floor and the wall,
  • and the power feed conduit wall penetrations.

The pit where the power conduits came through the wall and turned up into the power feed cabinets was 18″ deep, and always full of water.

The Challenge

Extensive exterior drainage work did not work. It presumed that surface water was flowing down the outside face of the basement wall. Then, through the unsealed floor:wall joint and/or into unsealed joints in the conduits and then through the conduit penetrations. The exterior drainage improvements re-waterproofed approximately 500sqft of wall. They slowed, but did not completely stop the water intrusion.

A forensic engineer overseeing the project reached out to CJGeo about performing chemical grouting inside of the utility room to underseal the floor, and to seal the conduit penetrations.

The Solution

CJGeo proposed chemical grouting utilizing a low viscosity hydrophobic prepolymer chemical grout.

Fibrous material soaked in grout was placed into the utility conduit openings to seal them against water intrusion. The grout injected through the floor extruded up through the joint between the wall and floor, and also through various cracks in the floor.

Upon completion of the basement water intrusion grouting by CJGeo, the conduit pit was dry, and there are no longer any leaks.

Speak With An Expert

Facing a similar challenge to this basement water intrusion grouting project? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Dollar Store Floor Void Filling

The Job

This floor void filling project is located about three hours west of Richmond, Virginia. A commercial contractor was performing a full gut renovation of a dollar store in a strip center. The building was approximately 30 years ago, and there were no signs of floor slab failure or settlement.

The Challenge

While cutting through the floor to install utilities, a 3″ void was discovered below the floor. Exploratory coring determined that voids ranged from 0.5 to 4″ throughout approximately 11,000 square feet of the space. The front of the building is at grade, but the rear of the building has an approximately 7′ tall CMU stem wall, which was backfilled with common borrow during original construction.

The Solution

The general contractor reached out to the structural engineer to notify them of the problem. The structural engineer then reached out to the geotechnical engineering, who recommended polyurethane grouting as the best way to fill voids below a floor. The geotechnical engineering is familiar with polyurethane grouting from working with CJGeo on similar repairs in the past. They know that polyurethane grouting:

  • is very clean and fast, so is unlikely to slow progress
  • is very lightweight, so is least likely of all grouts to cause additional settlement
  • effectively cures instantly, allowing immediate resumption of activities in the area

CJGeo mobilized two geotechnical polyurethane grouting crews to the site and filled the voids over a period of two days. It took about 7,000 pounds of CJGrout 20SDB through approximately 500, 5/8″ holes to completely fill the voids. Cut-off criteria was cross-hole communication. The work was performed without disruption to the renovation activities.

Speak With An Expert

Facing a similar challenge to this floor void filling project by CJGeo? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

25MGD Sinkhole Leak Grouting

The Job

An underground minerals mine started to lose up to 8VF per day of mine due to water infiltration. Investigation of an adjacent stream uncovered multiple sinkholes which had opened up where the stream crossed a fault. Two sinkholes were adjacent to bridge abutments of a public road, which served as the sole access for multiple homes and farms.

The Challenge

Mine personnel started to self-perform chemical grout in some of the sinkholes. Due to the slow rate of grout installation relative to the water flow, the self-performed grouting was unsuccessful.

Due to endangered fish habitats within the stream, cementitious grouts weren’t allowed, and any chemical grouts needed to be certified for potable water use.

The Solution

CJGeo mobilized two polyurethane grouting crews in the third week of the Covid-19 pandemic to the site. To facilitate safe access to the site, all grouting was performed from aerial platforms reaching out over the work area.

During the grouting process, multiple additional sinkholes opened up; CJGeo would seal one sinkhole, and an adjacent soil filled feature would blow out. Super sacs of aggregate were dropped in the sinkhole throats to fill the bulk of voids, and then polyurethane grouting was performed below the super sacs.

Using nearly 50,000 pounds of CJGrout 35NHV61, CJGeo was able to slow the leaks to the point where no additional sinkholes formed, and the mine’s pumps were able to dewater the facility.

Speak With An Expert

Facing a similar challenge to this project? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Sloped Pit Lightweight Backfill

The Job

This sloped pit lightweight backfill project is located in Western Virginia, at James Madison University. This work is part of the conversion the basketball arena at JMU in Harrisonburg, Virginia into a practice and competition facility for other sports.

The Challenge

An area of sloped stadium seating needed to be removed, and the mezzanine level floor extended over the sloped soil, which stayed in place, and onto a new wall at the toe of the slope. To reduce the likelihood of inducing settlement by adding up to 10 feet of backfill over the existing soils, the architect originally designed the backfill material as Expanded Polystyrene (EPS blocks). However, given the uneven soil slope, this would have been very challenging to install.

The general contractor reached out to CJGeo to see if there was a more practical load reducing fill.

The Solution

Working with the general contractor, architect and geotechnical EOR, CJGeo designed a backfill system that could be installed in fewer than six hours onsite, still provided a significant reduction in load, and cost significantly less than the foam blocks. The optimal product to meet the project criteria was 25lb/cuft CJFill-Ultra Lightweight low density flowable fill. CJFill-Ultra Lightweight has all the constructibility advantages of flowable fill, along with the following additional benefits:

  • is made at up to 200CY/hour onsite
  • provides up to 150CY of final material per load of raw material to the site
  • applies minimal lateral pressure on adjacent walls during installation
  • significantly reduces dead loads to underlying soils & structures

CJGeo generated the material onsite using dry batch generation, and placed the material in two lifts in order the limit the lateral loads on the new CMU wall during placement to 0.9psi.

Speak With An Expert

Facing a similar challenge to this sloped pit lightweight backfill project? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Lightweight Stem Wall Backfill

The Job

This lightweight stem wall backfill work is part of the construction of a new academic building at a school in Lynchburg, Virginia.

The Challenge

There was up to an 8′ difference in elevation between the existing ground and the desired finish floor elevation. Various options for filling the CMU stem walls included soil, aggregates and EPS foam blocks. EPS foam blocks were chosen to reduce loads on the footings. Otherwise, which would have required deep foundations in the case of soil or aggregate backfilling.

Due to the extensive sub-slab plumbing, the design called for EPS blocks cut to fit the curved walls & uneven ground profile, and then backfilled with 18″ of stone dust, to allow for the plumbers to dig and install the plumbing.

The Solution

The goal was to speed construction and reduce costs. CJGeo worked with the general contractor, structural engineer and geotechnical engineer to design a self-consolidating backfill system as a geofoam alternative. The final design for the lightweight stem wall backfill was 25lb/cuft CJFill-Ultra Lightweight load reducing backfill.

Using the dry batch generation process, a single CJGeo crew made up to two hundred cubic yards per hour of CJFill-UL. Pouring in two foot lifts, the work took about four days onsite. Instead of having to install an 18″ thick sand layer, the plumbers hand dug through the CJFill-UL to install the plumbing. Plumbing trenches were backfilled with stone dust.

Speak With An Expert

Facing a similar challenge to this lightweight stem wall backfill project? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Precast Lagging Wall Lateral Load Reduction

The Job

This load reduction backfill work as associated with the replacement of Scaife Hall, at Carnegie Mellon University, in Pittsburgh, Pennsylvania.

The Challenge

The H-pile and precast lagging wall is at the top of a steep slope. There is a Class I railroad line at the base. Because of site constraints, an HDPE stormwater detention structure is within the fill area. Along with extensive stormwater pipes and manholes.

In order to optimize the drilled shafts for the H-piles by reducing the lateral loads, the designer sought a lightweight, permeable backfill material that would not apply lateral loads once in place.

The Solution

CJGeo proposed 20lb/cuft CJFill-High Permeability cellular concrete. CJFill-HP would minimize lateral loading on the wall during construction, buoyancy of of the stormwater system components, and ensure a free draining material.

Because the material is permeable (modified ASTM D-2434 2.0cm/sec), it is freely draining and reduces hydrostatic loads on adjacent structures.

620 cubic yards of lightweight backfill were placed over two mobilizations to complete this load reduction backfill project.

Speak With An Expert

Facing a similar challenge to this retaining wall load reduction project? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

250000 Gallon Oil Tank Abandonment

The Job

This oil tank abandonment project is located in the nation’s capitol, Washington, DC. As part of decommissioning an underground oil tank at Howard University in Washington, DC, it needed to be filled with excavatable material that was lighter than the roughly 55lb/cuft heating oil it was designed to hold.

The tank is under a small empty lot. The lot is up for redevelopment in approximately three years.

The Challenge

For a complete decomissioning, the tank had to be completely full of grout. Since it sits within a planned basement excavation, the fill material has to be easily excavatable.

The Solution

CJGeo proposed 20lb/cuft cellular concrete for the oil tank abandonment grouting. This afforded plenty of factors of safety to reduce the likelihood of settlement induced by filling the tank and maximized excavatability. The removability modulus of 20lb/cuft (a quantifiable method for determining excavatability of various types of flowable fill) is much less than one. This means it is easily hand excavatable.

CJGeo placed the CJFill-Ultra Lightweight fill material over a period of two days onsite. Because cellular grout is highly mobile, no entry was required during the placement of the fill material, which designed a significant amount of risk out of the process.

The 1200CY placement was performed over two days onsite.

Speak With An Expert

Facing a similar challenge to this oil tank abandonment project? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Top