Industrial Driveway Crossing Repair

maryland modular grade crossing repair by CJGeo using polyurethane grouting

Industrial Grade Crossing Repair–Frederick, Maryland

Crossing Use:  

Heavy haul freight & passenger crossing an industrial facility driveway

Problem:

Settlement and deflection were affecting an eight panel modular grade crossing in an industrial driveway.    

Settlement of modular grade crossing was causing spalling of the panel edges due to more than 2 inches of deflection from rail traffic.

Constraints:

The repair had to quickly and thoroughly address the voids and settlement of the panels to avoid disruption to commuter revenue traffic.  A daily window of four hours between last morning and first afternoon commuter traffic was available for the repair.  

Due to scheduling constraints within the busy Washington, DC metro area freight market, the repair area had to be openable to freight traffic on 15 minute notice any time during the repair. 

Solution:

High density polyurethane polyurethane grouting to stabilize and lift the affected precast grade crossing panels.  

Polyurethane grouting is an effective repair for both void filling to address deflection, and also lifting panels to correct settlement.

Result:

CJGeo modular grade crossing repair crew filled the voids and corrected settlement in fewer than four hours.  

The crossing was returned to service without disruption to commuter or freight rail service.