I-66 Annular Space Grouting
The Job
During the widening of Interstate 66 near the interchange with US-15, nine new culverts were installed by jack and bore, and one via direct jacking. The carrier pipes were a mix of spiral metal, precast concrete, and corrugated HDPE, and ranged in length from 150 to 350 feet.
The Challenge
The contractor, who was responsible for grouting, was concerned about carrier pipe buoyancy during grouting, and also run length. All work had to be done from one side of the interstate highway (three lanes in each direction, plus full-width shoulders and a median strip), as there was no access on the far side.
The Solution
CJGeo proposed 30lb/cuft CJFill-Ultra Lightweight cellular concrete for the annular space grouting mix design. Cellular concrete is the preferred material for annular space grouting because it is highly flowable, and reduces the chances of damage to carrier pipes in long placements. Its low unit weight also reduces carrier pipe buoyancy. CJGeo placed 350CY of cellular grout to successfully complete the jack and bore annular space grouting over three different mobilizations.
Speak With An Expert
Facing a similar challenge to this project? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.
Virginia Annular Space Grouting
THE JOB
1100 feet of pile-supported 34″ PCCP water line over a drinking water reservoir was being slip-lined. This Newport News, Virginia annular space grouting project was specified by the designer to use cellular concrete. The relining contractor used 30″ welded HDPE for the slip line, which then required annular space grouting.
There were multiple leaks at the joints between the PCCP sticks. Work was complicated by a seasonal light display, which limited access hours to the job site.

THE CHALLENGE
The designer specified 55PCF wet cast density CJFill-Standard cellular concrete for the annular space grouting. Cellular concrete is highly flowable. High flowability ensures low installation pressure, reduces flotation of lightweight carrier pipes, and ensures complete void filling outside of the host pipe. Using cellular concrete for annular space grouting was specified by the HDPE slip lining pipe manufacturer. Buoyancy control was by water fill of the carrier pipe.
Nearly every joint on the pipe was leaking. Each joint had to be grout tight prior to starting the grouting process.
THE SOLUTION
All venting was over water. CJGeo completed this Virginia annular space grouting project without introducing any contaminants to the drinking water reservoir.
The 55PCF cellular concrete provided a break strength of approximately 700psi at 28 days. Peak installation pressure was 18psi. The crew used wet batch generation due to the relatively low volume.
Speak With An Expert
Facing a similar challenge to this Virginia annular space grouting project? Give us a shout or shoot us a text. Click the state marker for the location of the project for contact info for the appropriate rep.
Maryland Annular Space Grouting
THE JOB
A jack & bore contractor performed a 200LF, 54″ bore under an arterial highway. After sliding in a 48″ RCP carrier pipe (stormwater), the annular space required grouting. This Maryland annular space grouting project is located in Jessup.

THE CHALLENGE
Due to size limitations, only one end of the pipe was accessible for grouting. The length of the placement was approximately 200LF, so grout had to travel 200LF at low pressure while ensuring a complete fill.
THE SOLUTION
CJGeo proposed cellular concrete for the annular space grouting. Cellular concrete is highly flowable. High flowability ensures low installation pressure, reduces flotation of lightweight carrier pipes, and ensures complete void filling outside of the host pipe.
CJGeo successfully performed this Maryland annular space grouting project in a single day using CJFill-Ultra Lightweight cellular concrete. The peak pressure at the pump did not exceed 5PSI throughout the project.
Due to the relatively low volume, CJGeo used continuous wet batch generation for making the cellular concrete. With continuous wet batch generation, a ready mix company delivers the slurry. The ready mix truck discharges into a grout pump, and CJGeo injects the preformed foam continuously in line downstream of the pump.
Speak With An Expert
Facing a similar challenge? Give us a shout or shoot us a text. Click the state marker for the location of the project for contact info for the appropriate rep.
Emergency Pipe Abandonment
THE JOB
The pavement of a rural road outside of Williamsburg, Virginia collapsed suddenly. The pavement was adjacent to a golf cart tunnel, but there was nothing apparently wrong with the cart tunnel. VDOT closed the road to perform exploratory excavation. The exploratory excavation revealed a partially-collapsed RCP culvert pipe running adjacent to the golf cart tunnel. This required emergency pipe abandonment.

THE CHALLENGE
CJGeo had to mobilize with very little notice. The proposed grout had to have the ability to flow through the unknown obstructions in the collapsed RCP, and also out into any voids outside of the collapsed pipe.
THE SOLUTION
CJGeo proposed 30lb/cuft CJFill-Ultra Lightweight cellular grout due to its highly flowable characteristics. Cellular concrete is excellent for ensuring complete fills of collapsed or compromised pipes.
CJGeo mobilized to the site within one day and completed the emergency pipe abandonment in less than two hours. The road was opened back up to traffic immediately afterward.
The 30lb/cuft CJFill-Ultra Lightweight cellular grout that CJGeo placed on this project has an average strength of around 150psi at 28 days. However, it will accept foot traffic and equipment traffic within 12 hours. In this case, the collapsed pavement had already been reconstructed after the compromised pipe was identified. The Aerlite preformed foam was from Aerix Industries.
Speak With An Expert
Facing a similar challenge to this emergency pipe abandonment project? Give us a shout or shoot us a text. Click the state marker for the location of the project for contact info for the appropriate rep.
Power Conduit Abandonment
THE JOB
This power conduit abandonment project was part of a new line installation project. A utility contractor installed a new, upgraded parallel line. After switching service, pulling the electrical lines, and removing the oil, the contractor had to completely fill the lines with grout.
THE CHALLENGE
There are very few access points for high voltage power conduits. There were multiple runs over 3,500LF on this project, and it was neither safe nor practical to excavate down to the line at the frequent intervals required to fill the conduit with flowable fill.

THE SOLUTION
CJGeo proposed abandoning the conduit with CJFill-Ultra Lightweight cellular concrete. Cellular concrete is exceptionally high mobility grout. It’s easily pumpable thousands of feet at a time, at low pressure. Through careful planning with the client, CJGeo broke down the placement into 9 different runs, ranging from 200LF to 3800LF. Each placement utilized existing access points, such as vaults & terminations.
CJGeo successfully completed each run of power conduit abandonment. Pumping pressures never exceeded 30psi, and uniform grout showed at the vent end of each run to confirm complete fill. The work was performed over the winter, including multiple placements below freezing, and during the snow. The cellular concrete was generated using Aerlite preformed foam, by Aerix Industries, and continuous generation wet batching.
Speak With An Expert
Facing a similar challenge to this power conduit abandonment project? Give us a shout or shoot us a text. Click the state marker for the location of the project for contact info for the appropriate rep.
1 Mile 36″ Waterline Abandonment
THE JOB
CSX crews were surfacing the mainline track in Baltimore when the tamping equipment struck an object immediately below the ties. Investigation revealed that it was a manhole associated with nearly 6000LF of 36″ water main primarily running immediately below the tracks. The municipality relocated the waterline. Next, they had to fill the pipe from just two intermediate points. There were three sections of pipe; 1200LF, 1600LF & 2900LF. Various potential solutions for the watermain abandonment included:
- threading sacrificial tubing and grouting on the way out, and
- pumping flowable fill from the manholes,
However, none were economical or could guarantee a pipe abandonment below the railroad.
THE CHALLENGE
The project designer, OBG, identified cellular concrete as a potential solution to the problem and reached out to CJGeo to determine its feasibility. CJGeo confirmed the appropriateness of cellular concrete and set out to create a grouting plan. Coordination between the utility contractor and slurry provider (the site was too small to set up a batch plant) was crucial to ensure that the runs of pipe were all successfully filled in a single shot each. With train frequencies of 3-4 per hour, if the operation didn’t work and the pipes were only partially filled, there was no opportunity to create intermediate access points to finish grouting a section of pipe.

Based on the required bearing capacity and production requirements, CJGeo proposed 22lb/cuft CJFill-Ultra Lightweight cellular concrete for abandonment. With a 25psi break strength at 28 days, the mix provided the required strength, met the CSX utility occupancy standard for abandonment, and maximized expansion in order to ensure the longest run, which required nearly 1000CY of the finished product, could be grouting in a single shot.
THE SOLUTION
CJGeo mobilized a 150CY/hour cellular concrete crew to the site and performed the two shorter runs the first week. The project was broken into two different weeks due to the criticality of ensuring the longest run was filled completely without issue. The first two runs allowed CJGeo, the GC, railway flaggers, railway operations, and the slurry provider the opportunity to work out any kinks in operations during the lower risk placements.
The following Tuesday, starting at 0600, Chaney Enterprises delivered the first of 24 loads of slurry. Overall, the work took three days. CJGeo generated & pumped a total of 1710 cubic yards of cellular concrete to successfully complete the waterline abandonment.
This project would have been much easier using a mobile batch plant, which we now have three of.
Speak With An Expert
Facing a similar challenge to this waterline abandonment project? Give us a shout or shoot us a text. Click the state marker for the location of the project for contact info for the appropriate rep.
Fullerton Reservoir Annular Space Grouting
THE JOB
This reservoir annular space grouting project is located in Baltimore, Maryland. As part of the construction of a new drinking water reservoir for Baltimore County, Maryland, 140LF of 30″ jack & bore with a 12″ DIP water line and two 4″ PVC conduits required annular space grouting.
THE CHALLENGE
Due to the relatively long run and delicate PVC carrier pipes, CJGeo proposed using foamed concrete for the annular space grouting. 45lb/cuft CJFill-Standard cellular concrete generated using Aerlite preformed foam was proposed to achieve the owner’s requirement of 250psi at 28 days.
Carrier pipe buoyancy control is one of the most difficult elements of small diameter annular space grouting. In very large diameter placements, multiple lifts are practical, but in small diameter pipes, generally aren’t possible. When multi-lift grouting isn’t practical, having a grout density less than water (about 60 pounds per cubic foot) facilitates single lift grouting as long as the carrier pipes are full of water.

THE SOLUTION
In a short morning, they generated and placed 31 cubic yards of CJFill-Standard cellular concrete to successfully grout the annulus. Peak pumping pressure was less than 5psi. Confirmation of a complete fill was uniform material discharging from the 12 o’clock vent at the opposite end from placement.
Because the grout density was significantly less than the density of water, filling the carrier pipes with water controlled all buoyancy.
28 day breaks confirmed that CJGeo exceeded the break strength requirement.
Speak With An Expert
Facing a similar challenge to this Fullerton Reservoir annular space grouting project? Give us a shout or shoot us a text. Click the state marker for the location of the project for contact info for the appropriate rep.
MD 355 Lightweight Fill
THE JOB
As part of the construction of a pedestrian underpass at the Medical Center WMATA station, an open cut tunnel was installed. The tunnel crossed under MD-355, but over the underlying Metro Red Line tunnel. To maintain vehicular traffic during construction, a temporary bridge sat across two H-pile & lagging open cut walls.
After the tunnel was completed, the 7′ of space between the top of the new pedestrian tunnel and the bottom of the temporary bridge had to be filled. Numerous utilities, including:
- gas transmission mains,
- a power vault & duct bank,
- municipal water,
- gravity sewer,
- and numerous communication duct banks and lines,
All passed through the fill area. The tunnel designers needed lightweight fill material for the majority of the backfill to reduce loads on the new pedestrian tunnel.
The extensive utilities and limited working space made other lightweight fill materials. Alternates, such as EPS blocks and lightweight aggregate, were impractical to place. The Clark Foundations project team reached out to CJGeo to come up with a pumpable, self-consolidating lightweight fill solution.

THE CHALLENGE
CJGeo proposed using 30lb/cuft CJFill-Ultra Lightweight cellular concrete for the lightweight backfill. Cellular concrete had a few distinct advantages:
- Unit weight: the 30lb/cuft density met the designer’s requirement for unit weight. Low density grout also significantly reduces encased utility buoyancy during placement.
- Strength: the 125psi at 28 days strength far exceeded the requirement, and allowed for nearly immediate final backfill & paving
- Safety: time in the tunnel to set the grout placement pipes is minimal. No personnel are in tunnel during placement.
- Constructibility: aside from being lightweight, the primary concern was ensuring that all utilities were fully encapsulated. The fill had to go to within 12″ of the bottom of the temporary bridge beams. This would have been exceptionally difficult with any type of non-pumped lightweight fill.

THE SOLUTION
CJGeo mobilized a single low density cementitious fill crew to the site, capable of producing up to 150CY/hour of cellular concrete. Over the course of three days, CJGeo placed 990CY of 30lb/cuft non-pervious cellular concrete, using Aerlite preformed foam.
7 day breaks on the cellular concrete exceeded the minimum strength for backfilling. This allowed the customer to stay on their targeted schedule.
Speak With An Expert
Facing a similar challenge to this MD 355 lightweight fill project? Give us a shout or shoot us a text. Click the state marker for the location of the project for contact info for the appropriate rep.
Communication Jack & Bore Grouting
The Job
The Sandston area, just outside of Richmond, Virginia, is at the crossroads of major north/south data transmission lines, and transoceanic data transmission lines. This jack & bore grouting was done to support a road crossing connecting two new data centers.
The Challenge
As part of the construction of a new, multi-billion dollar data center, a utility contractor bored two, 48″ steel casings under a roadway & adjacent wet utilities for a road crossing. Each of the casings had up to 20 different PVC conduits held in place using casing spacers. The contractor needed a grout that could be placed at minimal pressure while ensuring complete fill without damaging the conduits.
To avoid carrier pipe buoyancy, the maximum allowable grout density for the annular space grouting was 45lb/cuft.
The Solution
CJGeo mobilized a cellular grouting crew to the site and did the jack & bore grouting on both pipes in a single day. The peak grouting pressure was 5psi, and confirmation of fill was achieved when uniform cellular concrete was vented from the 12 o’clock position on the opposite end of each bore. 38PCF CJFill-ST was used to achieve the design strength of 200psi at 28 days.
CJFill-ST is heavier than CJFill-Ultra Lightweight, which is the most common cellular grout that CJGeo uses for annular space grouting. However, in the case, the municipality specified a higher compressive strength due to the proximity of multiple other critical utilities.
CJGeo used wet batch on this project due to the low volume and proximity of a ready mix plant. Wet batch typically has lower peak heat of hydration, which is helpful when grouting around PVC.
Speak With An Expert
Facing a similar challenge to this communication jack & bore grouting project? Give us a shout or shoot us a text. Click the state marker for the location of the project for contact info for the appropriate rep.
Microtunnel Annular Space Grouting
The Job
This microtunnel annular space grouting project is part of a massive interstate expansion project in Charlotte, North Carolina. Seven micro tunnels were mined under I-77 to convey various utilities below the highway. Microtunneling was used, with casing diameters of 60″, along with a hand-mined tunnel lined with an 84″ tunnel liner plate.
Due to the length of runs, volumes required and strict NCDOT mix design requirements, the tunneling contractor reached out to CJGeo to explore cellular concrete as an option for the microtunnel annular space grouting.

The Challenge
CJGeo proposed performing the annular space grouting using 30lb/cuft cellular concrete. CJGeo has approved NCDOT mix designs for cellular concrete, which helped facilitate expedited submittal processing.
Cellular concrete was also advantageous from a carrier buoyancy perspective. The carrier pipes installed in each of the tunnels were all negatively buoyant in the grout. This helps to ensure proper alignment and minimize any chances of damage during grouting.
The Microtunnel Annular Space Grouting Solution
During the first mobilization, CJGeo placed 630CY of CJFill-Ultra Lightweight cellular grout to grout the two tunnels over a period of three days. The 60″ tunnel was grouted in a single lift, the 84″ tunnel was grouted in two lifts.
Confirmation of complete fill was through venting of uniform cellular concrete at the far ends of each tunnel. Additionally, the 84″ tunnel liner plate structure had cellular concrete weeping out of the bulkhead on the exterior of the plate. This indicates that the cellular concrete had exfiltrated through the liner plate joints and was flowing outside of the liner plate.
Speak With An Expert
Facing a similar challenge to this microtunnel annular space grouting project? Give us a shout or shoot us a text. Click the state marker for the location of the project for contact info for the appropriate rep.