Banner

Infrastructure

By applying unique solutions to increase the safety and longevity of our environment.

MD 355 Lightweight Fill

THE JOB

As part of the construction of a pedestrian underpass at the Medical Center WMATA station, an open cut tunnel was installed. The tunnel crossed under MD-355, but over the underlying Metro Red Line tunnel. To maintain vehicular traffic during construction, a temporary bridge sat across two H-pile & lagging open cut walls.  

After the tunnel was completed, the 7′ of space between the top of the new pedestrian tunnel and the bottom of the temporary bridge had to be filled. Numerous utilities, including:

  • gas transmission mains,
  • a power vault & duct bank,
  • municipal water,
  • gravity sewer,
  • and numerous communication duct banks and lines,

All passed through the fill area. The tunnel designers needed lightweight fill material for the majority of the backfill to reduce loads on the new pedestrian tunnel.

The extensive utilities and limited working space made other lightweight fill materials. Alternates, such as EPS blocks and lightweight aggregate, were impractical to place. The Clark Foundations project team reached out to CJGeo to come up with a pumpable, self-consolidating lightweight fill solution.  

md355-feature-2

THE CHALLENGE

CJGeo proposed using 30lb/cuft CJFill-Ultra Lightweight cellular concrete for the lightweight backfill. Cellular concrete had a few distinct advantages:

  • Unit weight: the 30lb/cuft density met the designer’s requirement for unit weight. Low density grout also significantly reduces encased utility buoyancy during placement.
  • Strength: the 125psi at 28 days strength far exceeded the requirement, and allowed for nearly immediate final backfill & paving
  • Safety: time in the tunnel to set the grout placement pipes is minimal. No personnel are in tunnel during placement.
  • Constructibility: aside from being lightweight, the primary concern was ensuring that all utilities were fully encapsulated. The fill had to go to within 12″ of the bottom of the temporary bridge beams. This would have been exceptionally difficult with any type of non-pumped lightweight fill.

THE SOLUTION

CJGeo mobilized a single low density cementitious fill crew to the site, capable of producing up to 150CY/hour of cellular concrete. Over the course of three days, CJGeo placed 990CY of 30lb/cuft non-pervious cellular concrete, using Aerlite preformed foam.

7 day breaks on the cellular concrete exceeded the minimum strength for backfilling. This allowed the customer to stay on their targeted schedule.

Speak With An Expert

Facing a similar challenge to this MD 355 lightweight fill project? Give us a shout or shoot us a text. Click the state marker for the location of the project for contact info for the appropriate rep.

Communication Jack & Bore Grouting

The Job

The Sandston area, just outside of Richmond, Virginia, is at the crossroads of major north/south data transmission lines, and transoceanic data transmission lines. This jack & bore grouting was done to support a road crossing connecting two new data centers.

The Challenge

As part of the construction of a new, multi-billion dollar data center, a utility contractor bored two, 48″ steel casings under a roadway & adjacent wet utilities for a road crossing. Each of the casings had up to 20 different PVC conduits held in place using casing spacers. The contractor needed a grout that could be placed at minimal pressure while ensuring complete fill without damaging the conduits.

To avoid carrier pipe buoyancy, the maximum allowable grout density for the annular space grouting was 45lb/cuft.

The Solution

CJGeo mobilized a cellular grouting crew to the site and did the jack & bore grouting on both pipes in a single day. The peak grouting pressure was 5psi, and confirmation of fill was achieved when uniform cellular concrete was vented from the 12 o’clock position on the opposite end of each bore. 38PCF CJFill-ST was used to achieve the design strength of 200psi at 28 days.

CJFill-ST is heavier than CJFill-Ultra Lightweight, which is the most common cellular grout that CJGeo uses for annular space grouting. However, in the case, the municipality specified a higher compressive strength due to the proximity of multiple other critical utilities.

CJGeo used wet batch on this project due to the low volume and proximity of a ready mix plant. Wet batch typically has lower peak heat of hydration, which is helpful when grouting around PVC.

Speak With An Expert

Facing a similar challenge to this communication jack & bore grouting project? Give us a shout or shoot us a text. Click the state marker for the location of the project for contact info for the appropriate rep.

Railway Grade Crossing Repair

THE JOB

112 track feet of crossing panels settled, and needed grade crossing repair. This caused the adjacent asphalt pavement to fail. The crossing ran diagonally across the highway. The road was graded so that the crossing was the primary flow path for surface water.

The crossing had already been replaced twice. The last replacement used flowable fill as the base material. The crossing panels experienced approximately 1 inch of deflection with highway traffic. There were also 4-inch voids below the panels.

amtrac-nj-grade-crossing-featured
Lifting modular grade crossing using polyurethane grouting.

With highway traffic from heavily-loaded vehicles, the crossing deflected enough to squirt water three to four feet in the air. This water pumping action actively pumped the subbase material from under the crossing.

THE CHALLENGE

The repair had to allow immediate vehicular traffic to facilitate a single-lane closure that was flipped halfway through the repair. The repair also had to allow for immediate resumption of rail traffic. The crossing served a sand mine. so the repair was designed around high service loads for heavy haul rail traffic.

THE SOLUTION

High-density polyurethane grouting using CJGrout 48NHL for this grade crossing repair.  CJGrout 48NHL is designed specifically for rail and airfield grouting work.

CJGeo modular grade crossing repair crew filled the voids and corrected settlement in less than a day.  Asphalt patching was done concurrently with polyurethane injection. The entire repair took less than one day. The roadway and rail opened up immediately after the repair.

Speak With An Expert

Facing a similar challenge to this railway grade crossing repair? Give us a shout or shoot us a text. Click the state marker for the location of the project for contact info for the appropriate rep.

Urban Grade Crossing

THE JOB

32 track feet of grade crossing panels settled. This caused the adjacent asphalt pavement to fail and caused tripping hazards at the adjacent pedestrian sidewalk. The grading in the area was relatively good, however, the adjacent ballast was fouled, which caused water to accumulate under the crossing panels and wash out the sandy subbase material. The crossing had been replaced recently. Due to the urban, primarily passenger automobile traffic, there was a little deflection of the crossing panels from highway traffic. However, there were up to four inches of deflection from rail traffic loading.

The deflection from rail traffic loading caused the top edges of adjacent panels to be in compression with each other. This caused extensive spalling of the surface, which affected two of the panels. While not a functional problem for panel integrity, the spalled areas were within the sidewalk portion of the crossings and therefore posed tripping hazards.

THE CHALLENGE

The repair had to allow immediate vehicular traffic to facilitate a single-lane closure. The repair also had to allow for immediate resumption of rail traffic. The crossing served as a sand mine, so the settlement correction repair was designed around high service loads for heavy haul rail traffic.

Due to the scheduling constraints of the railroad, the repair method had to tolerate the potential for rail traffic during the repair.

2015-12-27-14.28.57-300x225
Polyurethane grouting, asphalt patching, and panel patching.

THE SOLUTION

High-density polyurethane grouting to stabilize and lift the affected modular grade crossing panels, using CJGrout 48NHL.

Epoxy-augmented patching of the spalled areas to restore a smooth walkway for pedestrians.

CJGeo modular grade crossing repair crew filled the voids and corrected settlement in less than a day. Asphalt patching was done concurrently with polyurethane injection. The entire repair took less than two hours. The roadway and rail opened up immediately after the repair. Traffic control was done to accommodate pedestrians and roadway traffic.

Two trains passed through the crossing over the panels being repaired during the repair. This did not affect the integrity of the repair.

Speak With An Expert

Facing a similar challenge? Give us a shout or shoot us a text. Click the state marker for the location of the project for contact info for the appropriate rep.

Warehouse Floor Lifting

THE JOB

25,000 square feet of the industrial floor at a military facility settled up to 4 inches and was affected by sub-slab voids. This warehouse floor lifting project also included 250 track feet of embedded rail, which was set in an independent, thickened slab section. The building had been used for warehousing but was being transitioned to light manufacturing/maintenance.  

There were extensive voids below the floor. The voids were located with GPR, and confirmed with cores. Because the floor had cracked extensively as it settled, the designer called for a 4″ un-bonded overlay after stabilization.

THE CHALLENGE

The proposed repair method had to provide adequate bearing capacity for manufacturing and ensure complete void filling and stabilization.

THE SOLUTION

CJGeo provided a value engineering proposal to use geotechnical polyurethane instead of cementitious grout. The VE proposal was based on the following:

  • lower unit weight, so less likelihood of causing additional settlement
  • adequate strength to ensure uniform load transfer to the underlying soils
  • simplified logistics into a secure facility (all material delivered in just two truckloads)

The specified grout had an in-place density exceeding 115 pounds per cubic foot.  The proposed polyurethane grout, CJGrout 40NDV, has a constrained density of 5.5PCF, yet a bearing capacity exceeding 12KSF.

bldg-260-featured
Grouting in the area of the embedded rail tracks.

CJGeo mobilized three polyurethane grouting crews to the facility, with a combined pumping capacity exceeding 5,000 pounds per hour.  CJGeo crews injected the CJGrout 40NDV through nearly 2,000 dime-size holes drilled in the slab to complete this concrete lifting project.

The cutoff criteria for void filling was cross-hole communication or 0.1 inches of lift. The settled areas of floor raised an average of three inches. The embedded track area raised up to four inches.

It took CJGeo fewer than 10 days to complete this warehouse floor lifting job. Because the material cures to 95% within a few minutes, the overlay preparation crew worked a day behind the polyurethane grouting crews.

Speak With An Expert

Facing a similar challenge to this warehouse floor lifting project? Give us a shout or shoot us a text. Click the state marker for the location of the project for contact info for the appropriate rep.

Top