Pennsylvania Load Reducing Fill

Project Number: 2249

See Related Projects: Cellular Grouting | Lightweight Fill

The Job

CJGeo completed this Pennsylvania load-reducing fill project to support the replacement of Scaife Hall at Carnegie Mellon University in Pittsburgh.

scaife hall slide

The 25lb/cuft CJFill-HP in place.

The Challenge

The H-pile and precast lagging wall is at the top of a steep slope. There is a Class I railroad line at the base. Because of site constraints, an HDPE stormwater detention structure is within the fill area. Along with extensive stormwater pipes and manholes.

In order to optimize the drilled shafts for the H-piles by reducing the lateral loads, the designer sought a lightweight, permeable backfill material that would not apply lateral loads once in place.

The Solution

scaife featured

A tricky, but pretty, job site.

CJGeo proposed 20lb/cuft CJFill-High Permeability cellular concrete. CJFill-HP would minimize lateral loading on the wall during construction, buoyancy of of the stormwater system components, and ensure a free draining material.

Because the material is permeable (modified ASTM D-2434 2.0cm/sec), it is freely draining and reduces hydrostatic loads on adjacent structures.

CJGeo placed 620 cubic yards of lightweight backfill over two mobilizations to complete this load reduction project.

Speak With An Expert

Facing a similar challenge to this Pennsylvania load reducing fill project?

Connect

  • Contact Form
  • Call Us
  • LinkedIn

Explore Solutions

  • U
    Cellular Grouting
  • U
    Lightweight Fill

      Explore Services