The Job
This North Carolina low density cellular concrete project took place at the North Carolina museum complex in Raleigh. As part of a large campus renovation, HVAC system updates decommissioned a large underground chilled water storage tank. To ensure the long-term stability of the surrounding area, crews needed to completely fill the tank.

Placing the CJFill-UL low density cellular concrete
The Challenge
The structure sits below a central pedestrian plaza with difficult access. Engineers also worried that filling the tank with material heavier than water could cause settlement. Cost was another major driver, as the tank held a total volume of 3,800 cubic yards (785,000 gallons).
The Solution

CJGeo CJFill-UL batch plant.
CJGeo collaborated with the consulting engineers and general contractor to design a backfilling program. The team targeted an average in-place fill density of 62 lb/cuft. While crews can produce low density cellular concrete at 62 lb/cuft, it costs much more per cubic yard than ultra-lightweight cellular concrete.
To optimize cost and speed, the final design combined 1,200 cubic yards of traditional CLSM with a top layer of 28 lb/cuft CJFill-UL low density cellular concrete. This approach matched the total mass of the original water fill, minimizing the risk of settlement.
CJGeo mobilized a single dry batch cellular concrete plant to the site. The plant operated onsite for a few days and filled 20 VF of the tank.
Speak With An Expert
Facing a challenge similar to this North Carolina low density cellular concrete project?