The Job
This tunnel shaft sinkhole grouting project is located in Newport News, Virginia. It is located outside the gate for Pier 2 at Newport News Shipbuilding, home to the deactivated USS Enterprise (CVN-65). As part of water and sewer upgrades in the area, multiple shafts were excavated to facilitate guided pilot tube bores.
The Challenge
At a shaft in the middle of an intersection, the dewatering well driller was unable to maintain circulation. This resulted in incomplete dewatering points. During excavation of the ring beam and liner plate shaft, the floor blew out after excavating through a fat clay layer. The fat clay is underlain by a highly permeable flowing sand.
When the floor blew out, the shaft, which is roughly 30 feet diameter, settled up to a foot on one side, and the shaft flooded in a few minutes. Multiple large sinkholes opened up around the perimeter of the shaft.
The Solution
The utility contractor, who was sinking the shaft, reached out to CJGeo for a solution. The only way to salvage the situation was to adequately dewater the site, which was even less possible due to the extensive voids around the shaft.
CJGeo visited the site, and made a few recommendations. First was to grade the site to direct the surface water away from the structure. There were multiple blocks of surface stormwater flowing directly into the area around the shaft. Second was to perform polyurethane compaction grouting around the entire structure to fill voids under the pavement and around the liner plates.
CJGeo mobilized a geotechnical polyurethane grouting crew to the site the following day. Using CJGrout 35NHV61, the crew filled approximately 70 cubic yards of sinkholes. Grout uniformly migrated through the liner plates, indicating that voids were continuous around the perimeter, and across the full depth of the shaft.
After CJGeo completed the grouting work, the dewatering contractor was able to successfully drop four wells around the shaft. By dewatering the underlying flowing sands, the contractor was able to resume excavating the shaft.
A few weeks after stabilizing the shaft, the two tunnels were successfully completed from the shaft. A CJGeo cellular grouting crew then grouted the annular space on both tunnels.