Wisconsin Thermal Grouting

Project Number: 6194

The Job

This Wisconsin thermal grouting project by CJGeo is located in Sheboygan.  As part of a grid-scale battery storage installation, contractors had to bore transmission lines under multiple railroad tracks.  For ampacity management, the trenchless crossing required thermal grout in the bore annulus.

a red trenchbox with a stand hold up multiple pipe conduits coming out of a bore

Placing the CJTherm TM-5 thermal grout.

The Challenge

This jack and bore crossing is approximately 250 feet, and 36 inches in diameter.  The locally-available aggregate in the ready mix market was not suitable for achieving the specified thermal resistivity requirement.

The Solution

Red trench boxes with a worker and conduits at the bottom.

Site access.

CJGeo performed the thermal grouting using CJTherm TM-5 thermal grout mix.  Since locally available material wasn't available, we utilized material manufactured offsite and shipped in.  This approach removed all risk and cost of developing a project-specific mix for a low volume placement.

Pressure and temperature were monitored continuously and fed to the cloud.  Peak heat of hydration was less than 95°F.

Speak With An Expert

Facing a challenge similar to this Wisconsin thermal grouting job?

Connect

  • Contact Form
  • Call Us
  • LinkedIn

Explore Solutions

  • U
    Thermal Grouting

      Explore Services

      • U
        Annular Space Grouting
      • U
        Thermal Grouting