Banner

Cellular Concrete Projects

By applying unique solutions to increase the safety and longevity of our environment.

Savannah Tunnel Abandonment

The Job

This Savannah tunnel abandonment job is part of the JW Marriott Plant Riverside conversion. It’s an adaptive reuse hotel project of a decommissioned power plant in Savannah, Georgia. As a thermal generation facility, there are extensive water tunnels below the structure. The cast in place tunnels are part of the piled foundation.

The Challenge

As part of the conversion from thermal power generation to luxury hotel, the tunnels posed a maintenance concern. Due to concerns about inducing settlement with traditional flowable fill, the designer specified EPS Geofoam blocks. These would have effectively eliminated loads, but were deemed impossible to install.

The Solution

Someone onsite had heard of cellular concrete, so reached out to CJGeo. CJGeo evaluated the layout of the tunnels, isolation methods from the river, and designed a mix which would ensure both complete filling of the structures without adding any additional load.

CJGeo placed approximately 930CY of 20lb/cuft CJFill-UL cellular concrete over a period of three days to complete the Savannah tunnel abandonment. Because CJFill-UL is highly mobile, demo debris from the access holes for building bulkheads was left in the tunnels, and encapsulated with the CJFill-UL.

Speak With An Expert

Facing a similar challenge? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Nashville Basement Backfill

The Job

Nashville Yards is a block-wide new build project in downtown Nashville, Tennessee. With multiple underground levels of parking, this Nashville basement backfill excavation is more than 30′ below grade in spots. The excavation walls are a combination of blasted rock and soil nail walls.

The Challenge

The designer wanted to reduce lateral loading on the basement walls as much as possible. Due to the irregular face of the blasted rock & soil nail walls, lightweight aggregate would have been very difficult to install and compact, and would have applied lateral loads for the life of the structure. Flowable fill would have been easy to install, but applied too much lateral loading during installation if done in practical pour volumes.

The structural engineer determined that 25lb/cuft cellular concrete would be the best backfill material. The project volume was approximately 1500CY, and the maximum fill depth was 30′.

The Solution

CJGeo mobilized a mobile batch plant which uses colloidal mixing to the site. Due to the extremely high quality mixing, the crew placed CJFill-Ultra Lightweight up to 10′ deep per pour. This included three pours 10′ deep and 250CY each to complete this Nashville basement backfill project on time.

Speak With An Expert

Facing a similar challenge? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Veranda St Bridge Infill

The Job

This bridge infill work was part of Maine DOT’s Veranda Street Bridge Replacement Project, in Portland, Maine. Using rapid bridge replacement, the project took a three span bridge and converted it to a single span bridge.

The Challenge

To manage settlement due to up to 80′ of underlying WOH material, lightweight fill was needed to infill two spans, and backfill the new abutments. The absolute lowest unit weight possible requirement led to a hybrid cellular concrete/EPS fill design. The bulk of the infill is EPS blocks. However, due to the irregular surfaces, piers, etc., and the need for a lightweight load distribution slab, cellular concrete was integral to the design.

The Solution

Over two mobilizations for the bridge infill, through snow and freezing temperatures, CJGeo placed 3200CY of 25lb/cuft CJFill-Ultra Lightweight cellular concrete for abutment backfilling and existing pier infills. Then, CJGeo placed 778CY of 30lb/cuft CJFill-Ultra Lighweight as a topping slab over the EPS fill masses.

To ensure high quality material and minimize weather-related risks, CJGeo used onsite batching to generate the material. A mobile batch plant custom built for generating cellular concrete mixes water and dry bulk cement onsite. The cement paste and foam blend continuously to generate a completely homogenous material. With a slump of around 11.5 inches, both densities of CJFill-Ultra Lightweight cellular concrete were able to flow around all of the existing structures and provide a void-free fill.

Speak With An Expert

Facing a similar challenge? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Atlanta cellular concrete

The Job

This Atlanta cellular concrete installation is part of Atlanta Watershed Management’s Niles Avenue Sewer Improvements project. The project took approximately 2500LF of microtunneling to install a new 18″ sewer main.

The Challenge

A 72″ microtunnel was chosen, which required approximately 1200CY of annular space grouting. Operations were challenged by the pandemic hitting in the middle of the project.

The Solution

CJGeo proposed 30lb/cuft CJFill-UL cellular grout for the annular space grout. This allowed the contractor to avoid mechanical buoyancy control during grouting operations during single lift grouting. Buoyancy control of the carrier was one of the driving factors for using CJFill-Ultra Lightweight for this Atlanta cellular concrete project. Because the tunnels had a good amount of slope on them, grouting in multiple stages would have been impractical. Flowable fill would have floated the carrier pipe, even if it was full of water.

Over two mobilizations, CJGeo generated the cellular grout onsite and placed it via shafts which were up to 40 feet deep. CJGeo chose wet batch generation due to the project volumes.

Speak With An Expert

Facing a similar challenge? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Industrial Basement Abandonment

The Job

This industrial basement abandonment project is located in Southside, Virginia. As part of an adaptive reuse project of an abandoned industrial site, the former onsite power plant’s stacks were being rehabilitated. Multiple tunnels and basement rooms had to be completely filled.

The Challenge

Due to safety concerns, nobody could enter the basement. No as-builts were available. Camera inspection through holes cored in the ceiling showed significant numbers of passageways and obstructions. The fill material had to be:

  • exceptionally mobile,
  • placed in deep lifts,
  • and as light as possible.

Fill density was a concern because the basement was up to 15′ deep. 150lb/cuft traditional flowable fill would have caused too much anticipated settlement. Settlement of the basement structure could potentially cause settlement or movement of the adjacent smoke stacks.

The Solution

CJGeo proposed 25lb/cuft cellular concrete for the lightweight fill material. Using onsite colloidal batching, CJGeo can place material up to 20′ deep in a single lift, without consolidation. Because CJFill-Ultra Lightweight is so lightweight, the entire 15′ deep basement fill dead load was the same as from just 2′ of traditional flowable fill. For this application, Aerlite-iX was the most appropriate cellular concrete foaming agent.

CJGeo mobilized a 150CY/hour dry batch plant to the site after staging 300 tons of cement onsite using our in-house cement pig & trucking operation. Over four days onsite, CJGeo place 2700CY of CJFill-Ultra Lightweight material to complete the industrial basement abandonment.

Speak With An Expert

Facing a similar challenge? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

66″ Water Main Abandonment

The Job

This 66″ water main abandonment is part of the The Purple Line’s construction. The Purple Line is a light rail line project in suburban Maryland. It will increase connectivity within Maryland’s suburbs of Washington, DC. The project involves extensive utility relocation to facilitate installation of large embankments and the extensive infrastructure required for a double track rail corridor dropped into the middle of an already exceptionally congested/dense corridor.

The Challenge

As part of the project, a large MSE wall was built over approximately 3000LF of 66″ PCCP water main. To avoid any future maintenance problems under the rail alignment, a new line was put in adjacent to the embankment. The old line had to be completely full of grout.

Due to construction sequencing, the embankment installation happened before the water line relocation.

The Solution

CJGeo worked with the utility relocation contractor to design a grout mix and grouting program that provided sufficient bearing capacity to eliminate concerns about future stability. The ultimate design for the mix was a 100psi CJFill-Ultra Lightweight cellular grout. Because the embankment was already in place, the entire 3000LF stretch was accessible from just two access points.

CJGeo used a 200CY/hour dry mix batch plant onsite to generate and pump the cellular concrete up to 1500LF to place the material. This 66″ water main abandonment took four days to complete, and didn’t disrupt any of the adjacent construction activities.

Speak With An Expert

Facing a similar challenge? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Garden State Parkway grouting

The Job

This Garden State Parkway grouting project is located near Middletown, New Jersey. As part of ongoing large diameter culvert rehabilitations and replacements, four new bored stormwater crossings and the original culvert they replaced needed to be grouted. The tunnels ranged from 120″ down to 74″, for a total of 312CY, and the abandonment required 405CY.

The Challenge

Grout needed to meet the minimum strength requirements of the owner, and ideally needed to be light enough to facilitate single lift annular space grouting.

The Solution

CJGeo’s preconstruction team worked with the general contractor to design a grouting program which facilitated single lift abandonment of the original culvert, and single lift grouting of the four various annular space runs. CJGeo utilized onsite dry batching to generate 30lb/cuft CJFill Ultra Lightweight cellular concrete.

CJFill is a type of Low Density Controlled Low Strength Material, or LD-CLSM. The “low density” comes from using preformed foam, in this case Aerlite-iX, as a substitute for aggregate. This significantly reduces the unit weight, which exponentially increases pumpability. In this case, all 405 cubic yards of abandonment grout were placeable at once.

Because CJFill LD-CLSM is significantly lighter than water, each annular space grouting run was doable in a single lift. Filling each carrier pipe partially with water was all it took to facilitate this.

Speak With An Expert

Facing a similar challenge to this Garden State Parkway grouting project? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Lightweight Plaza Fill

The Job

Lightweight plaza fill for a private age restricted high rise new build in Tysons Corner, Virginia. Tysons Corner was historically an office heavy area of Fairfax County, but this project, along with many others, is increasing the amount of residential real estate in the area.

The Challenge

To manage dead loads over the four story parking deck, while achieving a landscape design requiring up to five feet of fill, the designer specified 20lb/cuft CJFill-High Permeability cellular concrete for the plaza fill material. The material had to be permeable, and placed up to 600′ from the closest access point for a plant. The deck elevation is about 30′ above the laydown area.

The total square footage of placement needed to be around 17,000 square feet. EPS foam blocks were an alternative fill material. However, EPS would have been exceptionally time consuming and expensive to install.

The Solution

CJGeo mobilized a 200CY/hour dry batch plant and crew, who generated up to 500CY/day for placement via hoses and a boom pump to successfully fill the plaza areas. Total project volume for this lightweight plaza fill was approximately 2200CY.

All material is onsite from dry bulk cement, with zero exposure to the hit or miss ready mix concrete market. An onsite cement storage pig allows overnight raw material delivery and staging, to eliminate traffic disruption.

The 20lb/cuft CJFill-High Permeability Low Density Controlled Low Strength Material placement was formed by the site concrete contractor. After the CJFill-HP had set, the site concrete contractor poured exposed aggregate sidewalks directly on top of the CJFill-HP. Other areas of the deck were backfilled with engineered lightweight soil, and then planted with extensive landscaping.

Speak With An Expert

Facing a similar challenge? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Hollow Abutment Filling

The Job

This hollow abutment filling project is located in Buckland, Massachusetts. Buckland is a small town on the east end of the Berkshires. The bridge conveys a rural highway over a drinking water impoundment. As part of a bridge rehabilitation for MassDOT, two hollow abutments were specified for filling. This would turn the structural approach/departure slabs into slab on grade. The alternative would have been to completely replace the structures. Filling them with traditional weight backfill would have caused significant settlement.

The Challenge

It was up to 30′ from the bottom of slab to the underlying soil which had originally been installed to backfill the abutments. The lightest possible material capable of providing sufficient support to the pavement was required. This would reduce the loads applied to the bridge from the backfill. Due to the very constrained access (a few cored holes through the deck, and a few square foot port cut into each abutment face), the lightweight material had to be self-consolidating (placed as a fluid).

Due to integrated beams for the structural slabs, there were 12 different individual pockets which were up to 2′ tall. Each had to be vent independently during the final lift. Four of were under live traffic because the road had to have one lane open at all times.

The Solution

CJGeo worked with the general contractor to formulate a plan to vent the individual pockets from outside of the open lanes. This helps to ensure a complete fill without requiring a complete road closure. Over the course of two mobilizations, CJGeo placed 2,840CY of 25lb/cuft CJFill-Ultra Lightweight to fill the abutments.

Speak With An Expert

Facing a similar challenge to this hollow abutment filling project? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

8″ Pipe Abandonment

The Job

This 8″ pipe abandonment project is located outside of Washington, DC. As part of continuing waterline replacements, a utility contractor in Fort Washington, Maryland, needed to abandon 10,600LF of 8″ water main. The utility and DOT both require grouting of all utilities 6″ and larger taken out of service.

The Challenge

In order to minimize the number of placement points, the grout needed to be exceptionally mobile.

The Solution

CJGeo proposed a 30lb/cuft CJFill-Ultra Lightweight (CJFill-UL) cellular grout, and worked with the client to design a grouting plan that would allow grouting all 10,600LF of pipe from just three access points. CJGeo performed the grouting over a period of two days, with no additional excavation required from the customer other than their original tie ins/disconnects.

By cutting the pipe at three locations, it was split into roughly equal segments. Each of around two thousand six hundred feet. 30lb/cuft CJFill-Ultra Lightweight is easily pumpable this distance without yield loss.

To do this same work with flowable fill would have required approximately thirty five access points. This would be to split the pipe into roughly thirty six segments around three hundred feet, each. Even then, pumping flowable fill three hundred feet through eight inch pipe is very difficult. By using CJFill-Ultra Lightweight for this pipe abandonment project, the general contractor saved about two weeks off of their schedule, and tens of thousands of dollars.

Speak With An Expert

Facing a similar challenge to this 8″ pipe abandonment project that CJGeo performed using cellular grout? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Top