Banner

Cellular Concrete Projects

By applying unique solutions to increase the safety and longevity of our environment.

Nashville Annular Space Grouting

The Job

This Nashville annular space grouting project is located at Nashville’s Central WWTP, which is undergoing extensive improvements to provide service to a growing population.

The Challenge

As part of an upgrade, 400LF of 66″ pipe was slip lined. Once the carrier pipe was selected, the space around its 57.1″ OD needed to be filled.

The Solution

CJGeo proposed using CJFill-ST at 45lb/cuft for this Nashville annular space grouting project. CJFill-ST is batched onsite directly from bulk cement, eliminating supply chain issues with ready mix.

Because the selected CJFill-ST only weigh 45lb/cuft, buoyancy control of the new carrier is simple. By filling it with water, it won’t float during grouting. This allowed CJGeo to grout the entire annulus in a single lift. Single lift grouting significantly reduces the likelihood of partial fills, fouled injection tubing, or trapped voids.

A CJGeo crew placed the 87CY of CJFill-ST in less than an hour to perform this Nashville annular space grouting project. CJFill-ST can be made two ways; wet batch or dry batch. With wet batch, a ready mix truck brings the base slurry to the site, and the foam is either added to the truck, or injected downstream of a pump. For dry batch generation, which was used here, a mobile batch plant mixes the cement and water onsite. The mixing quality using dry batch is significantly better than wet batch.

This project had a relatively high compressive strength requirement due to new foundation installation adjacent to the slip lined pipe. With cellular concrete, there are two ways to increase compressive strength–increase the cement content by increasing the density, or increasing the quality of the mix. Since annular space grouting projects are very sensitive to carrier pipe buoyancy control, increasing mix quality is a better option than increasing density. CJGeo’s three mobile batch plants all use high shear colloidal mixing. Colloidally generated material can have 28 day strengths up to two times ready mix batched material at the same density & cement content.

Speak With An Expert

Facing a similar challenge? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Pit Fill With Lightweight Flowable Fill

The Job

An abandoned water treatment plant at a federal facility was being rehabilitated and brought back into service. As part of the project, lightweight flowable fill was needed to fill a 12′ deep tank below the building floor needed to be filled before installing a new floor and equipment.

The Challenge

The majority of the pit is below ground water level. The original foundation design used a 62PCF fill density for the pits, presuming they would only ever hold water.

The backfill material also needed to completely encase a number of new micropiles installed for machine bases.

The designer had two competing interests–given the closeness of the water table to finish floor, avoid any buoyancy of the fill material, while using the lightest possible material to avoid inducing any settlement.

The Solution

CJGeo proposed filling the pit with CJFill-UW, at 70lbs/cuft. At 70lb/cuft, there are no uplift concerns, and the material is just barely denser than water, which helps minimize the amount of anticipated settlement. To help ensure future excavatability, CJGeo used a sanded base slurry (as opposed to the usual neat mix slurry) to generate 830CY of lightweight flowable fill material. The 28 day design strength was 150psi. The average 28 day tested compressive strength was 200psi. The removability modulus of the material is 0.75, which means the material is readily excavatable.

Traditional “lightweight” flowable fill is closer to 95lb/cuft. At 150psi, 95lb/cuft material has a removability modulus of 1.18. This is above ACI’s benchmark value of 1 for ease of excavatability.

For this project the CJFill-UW was generated by adding preformed foam to ready mix truck drums. The drum blends the slurry & foam as it rotates. The blended CJFill-UW discharges via the chute directly into the placement area.

Speak With An Expert

Facing a similar challenge? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Lightweight Temporary Dam Foundation

The Job

This lightweight temporary dam foundation installation was part of flood proofing project a nuclear power plant. The temporary dam can be quickly installed between two large structures in the case of anticipated storm surge. This is to keep flood waters from inundating a sensitive area.

The Challenge

The cooling water pipes for a reactor pass under where the dam goes in the case of a predicted flood. If placed, the dam exceeds the design load of the underlying cooling pipes.

The Solution

The designer elected to excavate 3′ of fill from above the pipes and replace it with 25lb/cuft CJFill-UL . Removing 3′ of 120lb/cuft material and replacing it with 3′ of 25lb/cuft, reduces dead load by roughly 275lb/sqft. The 25lb/cuft material can float, however. So, to address buoyancy, given the minimal cover (2″ of asphalt), geogrid cast into surrounding high density flowable fill acts as a hold down.

CJGeo poured the lightweight temporary dam foundation in two lifts. To void being in a cold joint, the geogrid was placed on sewer bricks. This ensures at least 6″ of embedment in the top layer of CJFill. To assess the readiness of the CJFill-Ultra Lightweight for paving, CJGeo cast a test slab for the customer to run heavy equipment over prior to loading the production area.

This was the first project where CJGeo utilized geogrid for buoyancy control of cellular concrete.

Speak With An Expert

Facing a similar challenge? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

BNA Culvert Abandonment

The Job

As part of a Nashville International Airport’s BNA Vision project, several hundred feet of culvert needed to be filled with grout. The culvert abandonment work is part of installing a new drainage system to accommodate a new terminal.

The Challenge

Due to long runs with no intermediate access, the engineer specified cellular concrete as the abandonment grout. Access to the site was across an active taxiway, so the fewest deliveries possible was very important. The minimum design requirements were:

  • 28 day compressive strength minimum = 100psi
  • maximum wet cast density = 35lb/cuft

The Solution

To address the need to limit the number of deliveries, CJGeo performed the culvert abandonment using CJFill-UL . CJFill-UL is batched onsite directly from bulk cement. By using bulk cement onsite, there were no concerns about hot loads of ready mix. A single semi was able to deliver all the raw material for the placement.

Each of the runs on this project is greater than 250LF. By using highly mobile grout, there are no questions about the pipes being completely full. CJFill-UL is so mobile it will flow by gravity up to a few hundred feet. The material is always pumped. This allows for placement from either the high or low end of individual runs. Because the density of the material is very low, it takes very little additional pressure to place from the low end.

Speak With An Expert

Facing a similar challenge? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Parsippany Annular Space Grouting

The Job

This Parsippany annular space grouting project is part of a microtunneled installation of 48″ sanitary line in two runs under an interstate. Each tunnel is 60″ diameter, one was 725LF, the other 530LF. They shared a shaft. The project’s goal is to replace an aging stretch of large diameter gravity sewer that runs parallel to the interstate.

The Challenge

The owner specified a grouted annular space for the tunnels. The long pumping distance and relatively tight annulus drove the need for a highly mobile, lightweight grout.

Cellular grout is advantageous for annular space grouting because:

  • it’s primarily air, so takes little energy (pressure) to pump, which virtually eliminates risk of damaging the carrier pipe(s) during grouting
  • it’s significantly lower density than traditional grouts, which reduces the buoyancy of carrier pipe(s)
  • cellular grout is made onsite, reducing risk exposures from the ready mix supply chain when mosts placements are “you only get once chance to do this right” type of jobs

The Solution

CJGeo placed 270CY of 35lb/cuft CJFill-ST (36ksf unconfined compressive strength) cellular grout to fill the annulus on both tunnels. Because the shared shaft wasn’t easily accessible, grouting was performed from each end towards the shared shaft over two back to back days.

CJGeo used onsite dry batching to generate the cellular grout for this Parsippany annular space grouting project. Dry batch generation uses bulk cement, eliminating risks associated with the ready mix supply chain. Cellular grout made using the dry batch process is also much higher quality, which allows CJGeo to get higher strengths with lower densities. This lowers pumping pressure, buoyancy, and costs.

Speak With An Expert

Facing a similar challenge? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Dumfries Pipe Abandonment

The Job

This utility relocation included abandonment grouting as part of a VDOT roadway reconstruction and realignment of US Route 1 in Dumfries, Virginia. This Dumfries pipe abandonment job is located in a rapidly growing town in Northern Virginia. US Route 1 is a major local traffic corridor, as well as a bailout route for I-95 congestion.

The Challenge

1,575LF of pipe, a combination of 54″ & 60″ needed to be completely filled with grout. Due to sequencing, the pipe was underneath new roadway at the time of abandonment. So, the fewer the number of access points, the better.

The Solution

CJGeo placed 995CY of 25lb/cuft CJFill-Ultra Lightweight cellular grout to completely fill the pipe run. The material was placed in a single day, from a single access point near the center of the pipe run.

To facilitate such a large placement in a single day on this Dumfries pipe abandonment job, CJGeo used dry batch generation. Dry batch generation mixed water with bulk cement onsite, using a mobile batch plant. CJGeo’s mobile batch plants are designed specifically to generate cellular concrete. They generate preformed foam at the same time as making the cement slurry. The preformed foam and cement slurry pass through an in line mixer, at up to 200CY/hour.

Speak With An Expert

Facing a similar challenge? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Lightweight Pipe Backfill

The Job

This lightweight pipe backfill is part of the City of Alexandria’s RiverRenew project, its largest in history. The project includes installation of new interceptors, and a large CSO/conveyance tunnel.

The Challenge

A pile-supported, concrete-encased interceptor needed to be backfilled. Due to the pile support capacity, the maximum allowable density of the backfill was 90lb/cuft.

The Solution

To bring the average backfill density to 90lb/cuft, CJGeo proposed filling between the SOE & concrete encasement with 30lb/cuft CJFill-High Permeability (HP). CJFill-HP has very high permeability, so reduces buoyancy when saturated when compared to other lightweight fill materials. CJGeo successfully filled between the concrete encasement and SOE with 145CY of CJFill-HP. The placements was done in a single, 6′ deep lift in less than an hour.

To facilitate the fast placement speed, CJGeo used a mobile batch plant to generate the CJFill-High Permeability cellular grout onsite. Onsite generation blends dry, bulk cement onsite with water, using custom batch plants which also make generate the preformed foam on site. The cement slurry is around 110lb/cuft, and the preformed foam is around 2.5lb/cuft. CJGeo’s batch plants utilize colloidal mixing, which ensures the highest quality cement paste, and therefore the highest quality finished product possible.

The use of very low density material then allowed the client to backfill on top of the structure with normal unit weight material while maintaining the average 90lb/cuft density through the full depth of the fill column.

Speak With An Expert

Facing a similar challenge? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Nashville Basement Abandonment

The Job

This Nashville basement abandonment project is located along Church Street, in downtown Nashville, Tennessee. A privately owned building was constructed inside of the basement of a previous building, but with a smaller footprint. Structural slabs spanning between 4′ and 20′ from the original basement walls to the new basement walls served as a parking lot and public sidewalk.

The Challenge

As the structural slabs over the unused basement deteriorated, there were concerns about stability. Uses included a public sidewalk and parking/driveway area. The wall isolating the occupied space of the new building and the unoccupied area of basement was constructed of hollow clay block, metal studs & drywall. The maximum lateral load of any backfill material could only be 50PSF.

The Solution

CJGeo successfully completed this Nashville basement abandonment with 775CY of 25lb/cuft CJFill-Ultra Lightweight cellular concrete. CJGeoGeo used 2′ lifts to meet the maximum 50PSF liquid head limit on the containing wall.

To address the unreliability of ready mix availability, CJGeo used the dry batch generation process to make the CJFill-UL onsite. Dry batch generation blends dry bulk cement and water onsite using a custom batch plant, which also generates the preformed foam. The cement slurry and preformed foam pass through a static mixer to ensure a homogenous mixture.

Because the roof slab was close to 18″ thick, and had multiple cast in place beams, CJGeo worked with the customer to design a sacrificial vent pipe system. This minimized the number of holes to core through the slab, while ensuring continuous bearing of the vault roof on the cellular concrete fill material.

Prior to placement of the CJFill-UL, a shotcrete contractor coated the hollow clay block wall to make it grout tight.

Speak With An Expert

Facing a similar challenge? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Steam Tunnel Lightweight Backfill

The Job

This steam tunnel lightweight backfill project is located at Western Carolina University, in Cullowhee, North Carolina. As part of the expansion and renovation of the steam plant, a section of existing steam tunnel needed to be uncovered to install a new wall. The wall needed to be backfilled, and due to the condition of the tunnel, the lighter the backfill the better.

The Challenge

The site was exceptionally tight, and the location was more than 30 minutes from the closest ready mix plant. The backfill depth was nearly 15 feet, but the project was only about 1200CY. So, doing 2′ lifts would have been slow and expensive.

To effectively eliminate axial loads from the tunnel, the structural engineer designed a cardboard void form system to temporarily support precast planks on top of the tunnel, which was approximately 5′ wide and 5′ tall. The planks extended about 18 inches beyond the sides of the tunnel. The void forms were wrapped in plastic. This ensured they wouldn’t be fouled by the CJFill-Ultra Lightweight cellular concrete during the pour. After the CJFill-UL was in place, the ends of the beams were encapsulated in, and bearing on, the cellular concrete, while spanning over the tunnel, and transferring the load of the backfill above the tunnel away from it.

The Solution

CJGeo proposed a CJFill-UL as a value improvement over the organic foaming agent cellular concrete that was specified. The architect and structural engineer approved the proposed change.

CJGeo mobilized a four person crew and a 200CY/hour mobile batch plant, and completed the steam tunnel lightweight backfill work in three pours over two days. The CJFill-UL was generated using a synthetic foaming agent. It can be placed up to 20 thick at a time, and is generated onsite directly from bulk cement, so isn’t dependent on ready mix plant locations.

Speak With An Expert

Facing a similar challenge? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

I-64 Soundwall Backfill

The Job

VDOT’s I-64 widening project is a multi-phase widening of Interstate 64 between Richmond & Newport News. This soundwall backfill work occurred as part of Segment 2, near the Queen’s Creek bridge.

The Challenge

Approximately 150LF of a combination sound & retaining wall needed to retain more than 10′ of backfill. In order to keep the drilled foundation size consistent along the alignment, the backfill material needed to be significantly lighter than the soil backfill used in other segments, where there was minimal retained depth.

The material needed to be freely-draining and less than 40lb/cuft. To ensure proper drainage, the lightweight fill material couldn’t impact the function of the combination drain waterproofing system applied to the wall.

The Solution

CJGeo proposed backfilling the affected wall segments with 30lb/cuft CJFill-UL. Used extensively by VDOT for backfilling the retained zones of MSE walls, CJFill-UL provides significantly better bearing capacity than soils or aggregates, and once cured does not apply lateral loads to the structures it is placed against.

During installation, lateral pressure from the cellular concrete is simply the hydraulic head. Hydraulic head is calculated by multiplying the pour thickness, in this case 5′, by the wet cast density, here 30lb/cuft, so 150PSF. Because CJFill-Ultra Lightweight cellular concrete does not contain any aggregate, there is no internal friction to contribute towards lowering pressures.

CJGeo placed approximately 200CY of CJFill-UL for the soundwall backfill the wall in two pours, each approximately 5′ thick. The contractor was able to place the pavement base on top of the material the following day.

Speak With An Expert

Facing a similar challenge? Give us a shout or shoot us a text. Click the state marker for the location of your project for contact info for the appropriate rep.

Top