RCP Pipe Sealing

RCP Pipe Sealing in Raleigh, NC area

Problem:

Asphalt parking lot over a 300′ run of 54″ RCP culvert kept collapsing. Public works department of locality determined that the joints between the 4′ sticks of pipe had not been properly gasketed or seated during installation. The pipe saw continuous flow of a small stream, entering at an end wall and discharging into a box culvert which crossed a public street. The drop inlet at the downstream junction between the RCP culvert and box culvert also had a failed 18″ RCP culvert feeding it, which had to be repaired multiple times using open trench excavation.

Extensive voids were identified around the pipe through an inspection. Much of the water flow from the stream was passing under/outside of the pipe, causing the erosion and collapse of the overhead parking lot, and the floor of a storage building built over the pipe. Previous attempts at sealing the joints and filling voids around the pipe with concrete had failed.

Solution:

Polyurethane grouting to fill voids around the pipe and seal the joints between the individual pieces of pipe, end wall and drop inlet. And, chemical grouting to treat a curtain at the upstream end to reduce subsurface flow, and at the downhill end to stabilize a joint in the failed small diameter RCP culvert entering the drop inlet.

Constraints:

Municipality was looking for an affordable, proven, and non-disruptive solution. Replacement would have required removal of a structure, and prevented adjacent businesses from using their parking lot during the work. Relining was not possible due to multiple sewer and water utility lines crossing through the pipe. Significant joint offsets would have also made lining difficult.

Grouting with a cement-based product was not a good option because any shifting in the pipe would have caused the grout to crack, and compromise its waterproofing ability.

Results:

CJGeo polyurethane grouting crews placed 50 cubic yards of NCFI high density, hydroinsensitive polyurethane and 45 gallons of polyurethane resin chemical grout over a period of three days to complete the repair. The repairs were all completed without disruption to the adjacent businesses or streets. Confined space ventilation and monitoring were completed by Concrete Jack’s crews.